PWRPA Dashboard — August 2026

2026 reconciliation · funds available · business unit activities

Sections 1a–1c: Actual January–Aug, estimated September–December 2026.

Hover any point or bar for detail · Ctrl/Cmd-P to print
2026 reconciliation

PWRPA — all participantsPWRPA

Metered load

344.5M kWh

vs 364.4M kWh budget

Total cost

$40.18M

vs $56.14M budget

Cost per kWh (w/o P3 or C&I)

11.66¢

vs 15.40¢ budget

Load covered by resource

97.3%

owned + contracted

1a

Monthly load, kWh

PWRPA — all participants

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M12.00M24.00M36.00M48.00M60.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 7.91M kWhFeb — 2025 actual: 8.55M kWhMar — 2025 actual: 12.01M kWhApr — 2025 actual: 22.47M kWhMay — 2025 actual: 35.83M kWhJun — 2025 actual: 41.12M kWhJul — 2025 actual: 39.40M kWhAug — 2025 actual: 34.86M kWhSep — 2025 actual: 25.64M kWhOct — 2025 actual: 17.78M kWhNov — 2025 actual: 9.08M kWhDec — 2025 actual: 7.44M kWhJan — 2026 budget: 14.31M kWhFeb — 2026 budget: 7.99M kWhMar — 2026 budget: 22.95M kWhApr — 2026 budget: 35.84M kWhMay — 2026 budget: 48.54M kWhJun — 2026 budget: 50.74M kWhJul — 2026 budget: 53.47M kWhAug — 2026 budget: 47.18M kWhSep — 2026 budget: 33.18M kWhOct — 2026 budget: 24.82M kWhNov — 2026 budget: 15.84M kWhDec — 2026 budget: 9.58M kWhJan — 2026 actual: 14.08M kWhFeb — 2026 actual: 7.78M kWhMar — 2026 actual: 22.24M kWhApr — 2026 actual: 34.51M kWhMay — 2026 actual: 47.41M kWhJun — 2026 actual: 48.98M kWhJul — 2026 actual: 51.34M kWhAug — 2026 actual: 44.08M kWhSep — 2026 actual (estimated): 25.48M kWhOct — 2026 actual (estimated): 24.00M kWhNov — 2026 actual (estimated): 15.34M kWhDec — 2026 actual (estimated): 9.27M kWh
1b

Resource mix

347.6M kWh owned + contracted
Base Resource: 197.96M kWh (57.0%)Generation - Slate (PV+BESS): 61.74M kWh (17.8%)Generation - Whitney Point: 30.38M kWh (8.7%)Generation - Astoria: 26.69M kWh (7.7%)Generation - LEC: 14.76M kWh (4.2%)District Specific Projects (BOR + WSH): 9.99M kWh (2.9%)Generation - Luna Valley: 5.31M kWh (1.5%)Supplemental: 0.74M kWh (0.2%)347.6MkWh total
ResourceEnergyShare
Base Resource197.96M57.0%
Generation - Slate (PV+BESS)61.74M17.8%
Generation - Whitney Point30.38M8.7%
Generation - Astoria26.69M7.7%
Generation - LEC14.76M4.2%
District Specific Projects (BOR + WSH)9.99M2.9%
Generation - Luna Valley5.31M1.5%
Supplemental0.74M0.2%
1c

Cost composition

Gross total $48.93M

Gross costs before resource credits and allocated overheads, so this totals $48.93M rather than the $40.18M net figure in the KPI row above.

OverheadOverhead: $2,362,535$2,362,535DistributionDistribution: $13,563,115$13,563,115TransmissionTransmission: $6,794,742$6,794,742Grid MgmtGrid Mgmt: $1,124,373$1,124,373LoadLoad: $11,392,546$11,392,546Power ResourcesPower Resources: $13,690,901$13,690,901
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)357,373,142$11,392,546$03.19¢$11,392,546
Specific Projects (BOR + WSH)9,992,000$25,963-$171,795-1.46¢-$145,832
Base Resource197,960,885$5,909,732-$6,939,297-0.52¢-$1,029,565
Generation — LEC14,757,891$2,314,797-$765,35410.50¢$1,549,443
Generation — Astoria26,688,303$1,725,263-$362,5055.11¢$1,362,758
Generation — Whitney Point30,376,893$1,779,067-$395,6944.55¢$1,383,373
Generation — Luna Valley5,314,764$112,898-$29,7621.56¢$83,136
Generation — Slate (PV+BESS)61,739,772$2,625,968-$1,109,9302.46¢$1,516,038
Supplemental744,000$244,257-$25,41129.41¢$218,846

Arvin-Edison WSDAEWSD

Metered load

113.5M kWh

vs 121.7M kWh budget

Total cost

$12.31M

vs $15.64M budget

Cost per kWh (w/o P3 or C&I)

10.85¢

vs 12.85¢ budget

Load covered by resource

91.6%

owned + contracted

1a

Monthly load, kWh

Arvin-Edison WSD

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M4.00M8.00M12.00M16.00M20.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 2.62M kWhFeb — 2025 actual: 2.42M kWhMar — 2025 actual: 4.29M kWhApr — 2025 actual: 8.64M kWhMay — 2025 actual: 14.24M kWhJun — 2025 actual: 16.01M kWhJul — 2025 actual: 14.06M kWhAug — 2025 actual: 13.57M kWhSep — 2025 actual: 11.39M kWhOct — 2025 actual: 7.14M kWhNov — 2025 actual: 2.03M kWhDec — 2025 actual: 0.64M kWhJan — 2026 budget: 8.72M kWhFeb — 2026 budget: 1.70M kWhMar — 2026 budget: 8.95M kWhApr — 2026 budget: 12.05M kWhMay — 2026 budget: 13.87M kWhJun — 2026 budget: 14.53M kWhJul — 2026 budget: 15.20M kWhAug — 2026 budget: 16.16M kWhSep — 2026 budget: 14.85M kWhOct — 2026 budget: 8.81M kWhNov — 2026 budget: 5.45M kWhDec — 2026 budget: 1.37M kWhJan — 2026 actual: 8.60M kWhFeb — 2026 actual: 1.65M kWhMar — 2026 actual: 8.63M kWhApr — 2026 actual: 11.64M kWhMay — 2026 actual: 13.63M kWhJun — 2026 actual: 14.14M kWhJul — 2026 actual: 14.58M kWhAug — 2026 actual: 15.50M kWhSep — 2026 actual (estimated): 10.02M kWhOct — 2026 actual (estimated): 8.53M kWhNov — 2026 actual (estimated): 5.27M kWhDec — 2026 actual (estimated): 1.33M kWh
1b

Resource mix

107.5M kWh owned + contracted
Base Resource: 62.79M kWh (58.4%)Generation - Slate (PV+BESS): 21.35M kWh (19.9%)Generation - Astoria: 10.23M kWh (9.5%)Generation - Whitney Point: 9.67M kWh (9.0%)Generation - LEC: 3.49M kWh (3.2%)107.5MkWh total
ResourceEnergyShare
Base Resource62.79M58.4%
Generation - Slate (PV+BESS)21.35M19.9%
Generation - Astoria10.23M9.5%
Generation - Whitney Point9.67M9.0%
Generation - LEC3.49M3.2%
1c

Cost composition

Gross total $15.04M

Gross costs before resource credits and allocated overheads, so this totals $15.04M rather than the $12.31M net figure in the KPI row above.

OverheadOverhead: $410,553$410,553DistributionDistribution: $3,904,262$3,904,262TransmissionTransmission: $2,376,795$2,376,795Grid MgmtGrid Mgmt: $352,343$352,343LoadLoad: $3,811,930$3,811,930Power ResourcesPower Resources: $4,183,790$4,183,790
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)117,364,502$3,811,930$03.25¢$3,811,930
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource62,791,821$1,898,826-$2,202,399-0.48¢-$303,573
Generation — LEC3,491,505$547,651-$181,07210.50¢$366,579
Generation — Astoria10,233,933$661,572-$139,0075.11¢$522,565
Generation — Whitney Point9,665,320$566,063-$125,9024.55¢$440,162
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)21,348,439$705,993-$325,8891.78¢$380,103
Supplemental0$51,344$0—$51,344

Banta-Carbona IDBCID

Metered load

17.5M kWh

vs 17.9M kWh budget

Total cost

$1.32M

vs $2.06M budget

Cost per kWh (w/o P3 or C&I)

7.57¢

vs 11.52¢ budget

Load covered by resource

85.2%

owned + contracted

1a

Monthly load, kWh

Banta-Carbona ID

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.80M1.60M2.40M3.20M4.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.02M kWhFeb — 2025 actual: 0.58M kWhMar — 2025 actual: 1.28M kWhApr — 2025 actual: 1.81M kWhMay — 2025 actual: 2.56M kWhJun — 2025 actual: 2.59M kWhJul — 2025 actual: 1.81M kWhAug — 2025 actual: 1.43M kWhSep — 2025 actual: 0.99M kWhOct — 2025 actual: 0.43M kWhNov — 2025 actual: 0.91M kWhDec — 2025 actual: 1.28M kWhJan — 2026 budget: 0.76M kWhFeb — 2026 budget: 1.01M kWhMar — 2026 budget: 2.19M kWhApr — 2026 budget: 2.12M kWhMay — 2026 budget: 3.02M kWhJun — 2026 budget: 2.54M kWhJul — 2026 budget: 2.15M kWhAug — 2026 budget: 1.51M kWhSep — 2026 budget: 1.50M kWhOct — 2026 budget: 1.00M kWhNov — 2026 budget: 0.05M kWhDec — 2026 budget: 0.05M kWhJan — 2026 actual: 0.76M kWhFeb — 2026 actual: 1.01M kWhMar — 2026 actual: 2.19M kWhApr — 2026 actual: 2.12M kWhMay — 2026 actual: 3.03M kWhJun — 2026 actual: 2.54M kWhJul — 2026 actual: 2.15M kWhAug — 2026 actual: 1.51M kWhSep — 2026 actual (estimated): 1.09M kWhOct — 2026 actual (estimated): 0.99M kWhNov — 2026 actual (estimated): 0.05M kWhDec — 2026 actual (estimated): 0.05M kWh
1b

Resource mix

14.9M kWh owned + contracted
Base Resource: 8.12M kWh (54.4%)Generation - Slate (PV+BESS): 4.76M kWh (31.9%)Generation - LEC: 1.31M kWh (8.8%)Supplemental: 0.74M kWh (5.0%)14.9MkWh total
ResourceEnergyShare
Base Resource8.12M54.4%
Generation - Slate (PV+BESS)4.76M31.9%
Generation - LEC1.31M8.8%
Supplemental0.74M5.0%
1c

Cost composition

Gross total $1.72M

Gross costs before resource credits and allocated overheads, so this totals $1.72M rather than the $1.32M net figure in the KPI row above.

OverheadOverhead: $98,604$98,604DistributionDistribution: $0$0TransmissionTransmission: $384,883$384,883Grid MgmtGrid Mgmt: $41,554$41,554LoadLoad: $484,282$484,282Power ResourcesPower Resources: $706,890$706,890
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)17,539,923$484,282$02.76¢$484,282
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource8,124,199$241,505-$270,725-0.36¢-$29,220
Generation — LEC1,313,079$205,960-$68,09710.50¢$137,862
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)4,761,190$303,508-$114,5513.97¢$188,958
Supplemental744,000$42,958-$25,4112.36¢$17,547

Byron-Bethany IDBBID

Metered load

2.5M kWh

vs 2.9M kWh budget

Total cost

$0.35M

vs $0.55M budget

Cost per kWh (w/o P3 or C&I)

13.92¢

vs 18.68¢ budget

Load covered by resource

135.1%

owned + contracted

1a

Monthly load, kWh

Byron-Bethany ID

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.10M0.20M0.30M0.40M0.50Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.02M kWhFeb — 2025 actual: 0.01M kWhMar — 2025 actual: 0.16M kWhApr — 2025 actual: 0.37M kWhMay — 2025 actual: 0.22M kWhJun — 2025 actual: 0.00M kWhJul — 2025 actual: 0.00M kWhAug — 2025 actual: 0.00M kWhSep — 2025 actual: 0.16M kWhOct — 2025 actual: 0.31M kWhNov — 2025 actual: 0.01M kWhDec — 2025 actual: 0.00M kWhJan — 2026 budget: 0.00M kWhFeb — 2026 budget: 0.00M kWhMar — 2026 budget: 0.24M kWhApr — 2026 budget: 0.32M kWhMay — 2026 budget: 0.40M kWhJun — 2026 budget: 0.45M kWhJul — 2026 budget: 0.43M kWhAug — 2026 budget: 0.42M kWhSep — 2026 budget: 0.32M kWhOct — 2026 budget: 0.27M kWhNov — 2026 budget: 0.06M kWhDec — 2026 budget: 0.03M kWhJan — 2026 actual: 0.00M kWhFeb — 2026 actual: 0.00M kWhMar — 2026 actual: 0.24M kWhApr — 2026 actual: 0.31M kWhMay — 2026 actual: 0.39M kWhJun — 2026 actual: 0.45M kWhJul — 2026 actual: 0.42M kWhAug — 2026 actual: 0.35M kWhSep — 2026 actual (estimated): 0.00M kWhOct — 2026 actual (estimated): 0.27M kWhNov — 2026 actual (estimated): 0.06M kWhDec — 2026 actual (estimated): 0.03M kWh
1b

Resource mix

3.5M kWh owned + contracted
Base Resource: 2.12M kWh (61.5%)Generation - Slate (PV+BESS): 0.71M kWh (20.6%)Generation - LEC: 0.62M kWh (17.9%)3.5MkWh total
ResourceEnergyShare
Base Resource2.12M61.5%
Generation - Slate (PV+BESS)0.71M20.6%
Generation - LEC0.62M17.9%
1c

Cost composition

Gross total $0.43M

Gross costs before resource credits and allocated overheads, so this totals $0.43M rather than the $0.35M net figure in the KPI row above.

OverheadOverhead: $61,371$61,371DistributionDistribution: $89,885$89,885TransmissionTransmission: $48,696$48,696Grid MgmtGrid Mgmt: $8,631$8,631LoadLoad: $77,299$77,299Power ResourcesPower Resources: $147,061$147,061
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)2,557,830$77,299$03.02¢$77,299
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource2,124,962$55,205-$74,274-0.90¢-$19,070
Generation — LEC618,863$97,070-$32,09510.50¢$64,976
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)712,384$33,146-$13,6182.74¢$19,527
Supplemental0-$1,009$0—-$1,009

Cawelo WDCWD

Metered load

17.2M kWh

vs 17.3M kWh budget

Total cost

$2.09M

vs $2.58M budget

Cost per kWh (w/o P3 or C&I)

12.15¢

vs 14.86¢ budget

Load covered by resource

99.0%

owned + contracted

1a

Monthly load, kWh

Cawelo WD

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.80M1.60M2.40M3.20M4.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.02M kWhFeb — 2025 actual: 0.05M kWhMar — 2025 actual: 0.47M kWhApr — 2025 actual: 1.32M kWhMay — 2025 actual: 1.96M kWhJun — 2025 actual: 3.39M kWhJul — 2025 actual: 3.84M kWhAug — 2025 actual: 3.32M kWhSep — 2025 actual: 1.96M kWhOct — 2025 actual: 0.84M kWhNov — 2025 actual: 0.03M kWhDec — 2025 actual: 0.03M kWhJan — 2026 budget: 0.03M kWhFeb — 2026 budget: 0.03M kWhMar — 2026 budget: 0.91M kWhApr — 2026 budget: 1.14M kWhMay — 2026 budget: 2.49M kWhJun — 2026 budget: 2.93M kWhJul — 2026 budget: 3.78M kWhAug — 2026 budget: 3.65M kWhSep — 2026 budget: 1.39M kWhOct — 2026 budget: 0.65M kWhNov — 2026 budget: 0.27M kWhDec — 2026 budget: 0.08M kWhJan — 2026 actual: 0.02M kWhFeb — 2026 actual: 0.03M kWhMar — 2026 actual: 0.89M kWhApr — 2026 actual: 1.12M kWhMay — 2026 actual: 2.43M kWhJun — 2026 actual: 2.83M kWhJul — 2026 actual: 3.63M kWhAug — 2026 actual: 3.51M kWhSep — 2026 actual (estimated): 1.76M kWhOct — 2026 actual (estimated): 0.63M kWhNov — 2026 actual (estimated): 0.26M kWhDec — 2026 actual (estimated): 0.08M kWh
1b

Resource mix

17.6M kWh owned + contracted
Generation - Slate (PV+BESS): 9.86M kWh (56.0%)Base Resource: 5.03M kWh (28.6%)Generation - Astoria: 1.60M kWh (9.1%)Generation - LEC: 1.11M kWh (6.3%)17.6MkWh total
ResourceEnergyShare
Generation - Slate (PV+BESS)9.86M56.0%
Base Resource5.03M28.6%
Generation - Astoria1.60M9.1%
Generation - LEC1.11M6.3%
1c

Cost composition

Gross total $2.45M

Gross costs before resource credits and allocated overheads, so this totals $2.45M rather than the $2.09M net figure in the KPI row above.

OverheadOverhead: $92,764$92,764DistributionDistribution: $537,123$537,123TransmissionTransmission: $369,381$369,381Grid MgmtGrid Mgmt: $73,883$73,883LoadLoad: $581,530$581,530Power ResourcesPower Resources: $800,299$800,299
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)17,768,431$581,530$03.27¢$581,530
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource5,031,196$159,938-$180,730-0.41¢-$20,791
Generation — LEC1,105,114$173,340-$57,31210.50¢$116,028
Generation — Astoria1,598,620$103,343-$21,7145.11¢$81,629
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)9,857,746$444,210-$184,3682.64¢$259,842
Supplemental0-$2,430$0—-$2,430

Glenn-Colusa IDGCID

Metered load

11.4M kWh

vs 11.5M kWh budget

Total cost

$1.07M

vs $1.53M budget

Cost per kWh (w/o P3 or C&I)

9.37¢

vs 13.32¢ budget

Load covered by resource

93.1%

owned + contracted

1a

Monthly load, kWh

Glenn-Colusa ID

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.60M1.20M1.80M2.40M3.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.20M kWhFeb — 2025 actual: 0.04M kWhMar — 2025 actual: 0.10M kWhApr — 2025 actual: 0.60M kWhMay — 2025 actual: 2.00M kWhJun — 2025 actual: 2.27M kWhJul — 2025 actual: 2.32M kWhAug — 2025 actual: 1.68M kWhSep — 2025 actual: 0.54M kWhOct — 2025 actual: 0.88M kWhNov — 2025 actual: 1.08M kWhDec — 2025 actual: 0.64M kWhJan — 2026 budget: 0.04M kWhFeb — 2026 budget: 0.07M kWhMar — 2026 budget: 0.19M kWhApr — 2026 budget: 0.46M kWhMay — 2026 budget: 1.94M kWhJun — 2026 budget: 2.11M kWhJul — 2026 budget: 2.41M kWhAug — 2026 budget: 1.81M kWhSep — 2026 budget: 0.49M kWhOct — 2026 budget: 0.69M kWhNov — 2026 budget: 0.76M kWhDec — 2026 budget: 0.50M kWhJan — 2026 actual: 0.04M kWhFeb — 2026 actual: 0.07M kWhMar — 2026 actual: 0.19M kWhApr — 2026 actual: 0.46M kWhMay — 2026 actual: 1.93M kWhJun — 2026 actual: 2.09M kWhJul — 2026 actual: 2.38M kWhAug — 2026 actual: 1.78M kWhSep — 2026 actual (estimated): 0.54M kWhOct — 2026 actual (estimated): 0.68M kWhNov — 2026 actual (estimated): 0.74M kWhDec — 2026 actual (estimated): 0.49M kWh
1b

Resource mix

10.7M kWh owned + contracted
Base Resource: 6.55M kWh (61.0%)Generation - Slate (PV+BESS): 1.78M kWh (16.6%)Generation - Astoria: 0.85M kWh (7.9%)Generation - Whitney Point: 0.83M kWh (7.7%)Generation - LEC: 0.74M kWh (6.9%)10.7MkWh total
ResourceEnergyShare
Base Resource6.55M61.0%
Generation - Slate (PV+BESS)1.78M16.6%
Generation - Astoria0.85M7.9%
Generation - Whitney Point0.83M7.7%
Generation - LEC0.74M6.9%
1c

Cost composition

Gross total $1.34M

Gross costs before resource credits and allocated overheads, so this totals $1.34M rather than the $1.07M net figure in the KPI row above.

OverheadOverhead: $93,041$93,041DistributionDistribution: $180,736$180,736TransmissionTransmission: $217,336$217,336Grid MgmtGrid Mgmt: $44,350$44,350LoadLoad: $381,834$381,834Power ResourcesPower Resources: $427,264$427,264
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)11,530,697$381,834$03.31¢$381,834
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource6,547,502$200,903-$239,884-0.60¢-$38,981
Generation — LEC740,983$116,225-$38,42810.50¢$77,797
Generation — Astoria845,757$54,674-$11,4885.11¢$43,186
Generation — Whitney Point828,378$48,515-$10,7914.55¢$37,725
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)1,777,754$51,947-$25,1691.51¢$26,777
Supplemental0$1,383$0—$1,383

James IDJID

Metered load

2.6M kWh

vs 2.6M kWh budget

Total cost

$0.39M

vs $0.69M budget

Cost per kWh (w/o P3 or C&I)

15.26¢

vs 26.68¢ budget

Load covered by resource

114.0%

owned + contracted

1a

Monthly load, kWh

James ID

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.12M0.24M0.36M0.48M0.60Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.04M kWhFeb — 2025 actual: 0.08M kWhMar — 2025 actual: 0.01M kWhApr — 2025 actual: 0.07M kWhMay — 2025 actual: 0.13M kWhJun — 2025 actual: 0.23M kWhJul — 2025 actual: 0.26M kWhAug — 2025 actual: 0.19M kWhSep — 2025 actual: 0.05M kWhOct — 2025 actual: 0.03M kWhNov — 2025 actual: 0.02M kWhDec — 2025 actual: 0.01M kWhJan — 2026 budget: 0.01M kWhFeb — 2026 budget: 0.05M kWhMar — 2026 budget: 0.12M kWhApr — 2026 budget: 0.03M kWhMay — 2026 budget: 0.27M kWhJun — 2026 budget: 0.50M kWhJul — 2026 budget: 0.46M kWhAug — 2026 budget: 0.32M kWhSep — 2026 budget: 0.38M kWhOct — 2026 budget: 0.25M kWhNov — 2026 budget: 0.18M kWhDec — 2026 budget: 0.01M kWhJan — 2026 actual: 0.01M kWhFeb — 2026 actual: 0.05M kWhMar — 2026 actual: 0.12M kWhApr — 2026 actual: 0.03M kWhMay — 2026 actual: 0.27M kWhJun — 2026 actual: 0.49M kWhJul — 2026 actual: 0.45M kWhAug — 2026 actual: 0.31M kWhSep — 2026 actual (estimated): 0.41M kWhOct — 2026 actual (estimated): 0.24M kWhNov — 2026 actual (estimated): 0.18M kWhDec — 2026 actual (estimated): 0.01M kWh
1b

Resource mix

3.0M kWh owned + contracted
Base Resource: 1.31M kWh (44.0%)Generation - Slate (PV+BESS): 0.59M kWh (19.9%)Generation - LEC: 0.59M kWh (19.7%)Generation - Whitney Point: 0.28M kWh (9.3%)Generation - Astoria: 0.22M kWh (7.2%)3.0MkWh total
ResourceEnergyShare
Base Resource1.31M44.0%
Generation - Slate (PV+BESS)0.59M19.9%
Generation - LEC0.59M19.7%
Generation - Whitney Point0.28M9.3%
Generation - Astoria0.22M7.2%
1c

Cost composition

Gross total $0.45M

Gross costs before resource credits and allocated overheads, so this totals $0.45M rather than the $0.39M net figure in the KPI row above.

OverheadOverhead: $63,564$63,564DistributionDistribution: $92,887$92,887TransmissionTransmission: $50,225$50,225Grid MgmtGrid Mgmt: $8,424$8,424LoadLoad: $90,616$90,616Power ResourcesPower Resources: $144,387$144,387
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)2,613,894$90,616$03.47¢$90,616
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,310,146$40,060-$48,873-0.67¢-$8,813
Generation — LEC585,909$91,901-$30,38610.50¢$61,516
Generation — Astoria215,098$13,905-$2,9225.11¢$10,983
Generation — Whitney Point276,126$16,172-$3,5974.55¢$12,575
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)592,585$17,316-$8,3901.51¢$8,926
Supplemental0-$630$0—-$630

Lower Tule River IDLTRID

Metered load

9.4M kWh

vs 10.0M kWh budget

Total cost

$0.99M

vs $1.23M budget

Cost per kWh (w/o P3 or C&I)

10.53¢

vs 12.27¢ budget

Load covered by resource

31.6%

owned + contracted

1a

Monthly load, kWh

Lower Tule River ID

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.40M0.80M1.20M1.60M2.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.25M kWhFeb — 2025 actual: 0.22M kWhMar — 2025 actual: 0.37M kWhApr — 2025 actual: 0.58M kWhMay — 2025 actual: 1.01M kWhJun — 2025 actual: 1.27M kWhJul — 2025 actual: 1.46M kWhAug — 2025 actual: 1.12M kWhSep — 2025 actual: 0.73M kWhOct — 2025 actual: 0.40M kWhNov — 2025 actual: 0.13M kWhDec — 2025 actual: 0.28M kWhJan — 2026 budget: 0.38M kWhFeb — 2026 budget: 0.21M kWhMar — 2026 budget: 0.59M kWhApr — 2026 budget: 0.60M kWhMay — 2026 budget: 1.07M kWhJun — 2026 budget: 1.42M kWhJul — 2026 budget: 1.59M kWhAug — 2026 budget: 1.47M kWhSep — 2026 budget: 1.06M kWhOct — 2026 budget: 0.79M kWhNov — 2026 budget: 0.57M kWhDec — 2026 budget: 0.30M kWhJan — 2026 actual: 0.35M kWhFeb — 2026 actual: 0.19M kWhMar — 2026 actual: 0.55M kWhApr — 2026 actual: 0.57M kWhMay — 2026 actual: 1.01M kWhJun — 2026 actual: 1.33M kWhJul — 2026 actual: 1.48M kWhAug — 2026 actual: 1.37M kWhSep — 2026 actual (estimated): 1.03M kWhOct — 2026 actual (estimated): 0.74M kWhNov — 2026 actual (estimated): 0.53M kWhDec — 2026 actual (estimated): 0.29M kWh
1b

Resource mix

3.2M kWh owned + contracted
Base Resource: 3.18M kWh (100.0%)3.2MkWh total
ResourceEnergyShare
Base Resource3.18M100.0%
1c

Cost composition

Gross total $1.11M

Gross costs before resource credits and allocated overheads, so this totals $1.11M rather than the $0.99M net figure in the KPI row above.

OverheadOverhead: $77,456$77,456DistributionDistribution: $350,187$350,187TransmissionTransmission: $199,864$199,864Grid MgmtGrid Mgmt: $32,801$32,801LoadLoad: $351,306$351,306Power ResourcesPower Resources: $102,003$102,003
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)10,050,083$351,306$03.50¢$351,306
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource3,179,875$104,159-$119,935-0.50¢-$15,776
Generation — LEC0$0$0—$0
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)0$0$0—$0
Supplemental0-$1,539$0—-$1,539

Princeton Prov IDPPID

Metered load

3.2M kWh

vs 3.3M kWh budget

Total cost

$0.42M

vs $0.68M budget

Cost per kWh (w/o P3 or C&I)

13.17¢

vs 20.49¢ budget

Load covered by resource

104.7%

owned + contracted

1a

Monthly load, kWh

Princeton Prov ID

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.18M0.36M0.54M0.72M0.90Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.01M kWhFeb — 2025 actual: 0.01M kWhMar — 2025 actual: 0.01M kWhApr — 2025 actual: 0.33M kWhMay — 2025 actual: 0.81M kWhJun — 2025 actual: 0.88M kWhJul — 2025 actual: 0.73M kWhAug — 2025 actual: 0.39M kWhSep — 2025 actual: 0.04M kWhOct — 2025 actual: 0.36M kWhNov — 2025 actual: 0.26M kWhDec — 2025 actual: 0.16M kWhJan — 2026 budget: 0.00M kWhFeb — 2026 budget: 0.00M kWhMar — 2026 budget: 0.00M kWhApr — 2026 budget: 0.16M kWhMay — 2026 budget: 0.61M kWhJun — 2026 budget: 0.57M kWhJul — 2026 budget: 0.47M kWhAug — 2026 budget: 0.22M kWhSep — 2026 budget: 0.06M kWhOct — 2026 budget: 0.51M kWhNov — 2026 budget: 0.43M kWhDec — 2026 budget: 0.25M kWhJan — 2026 actual: 0.00M kWhFeb — 2026 actual: 0.00M kWhMar — 2026 actual: 0.00M kWhApr — 2026 actual: 0.16M kWhMay — 2026 actual: 0.60M kWhJun — 2026 actual: 0.56M kWhJul — 2026 actual: 0.46M kWhAug — 2026 actual: 0.21M kWhSep — 2026 actual (estimated): 0.01M kWhOct — 2026 actual (estimated): 0.50M kWhNov — 2026 actual (estimated): 0.42M kWhDec — 2026 actual (estimated): 0.25M kWh
1b

Resource mix

3.4M kWh owned + contracted
Base Resource: 1.63M kWh (47.6%)Generation - LEC: 0.62M kWh (18.1%)Generation - Slate (PV+BESS): 0.59M kWh (17.3%)Generation - Astoria: 0.30M kWh (8.8%)Generation - Whitney Point: 0.28M kWh (8.1%)3.4MkWh total
ResourceEnergyShare
Base Resource1.63M47.6%
Generation - LEC0.62M18.1%
Generation - Slate (PV+BESS)0.59M17.3%
Generation - Astoria0.30M8.8%
Generation - Whitney Point0.28M8.1%
1c

Cost composition

Gross total $0.49M

Gross costs before resource credits and allocated overheads, so this totals $0.49M rather than the $0.42M net figure in the KPI row above.

OverheadOverhead: $63,228$63,228DistributionDistribution: $117,582$117,582TransmissionTransmission: $27,483$27,483Grid MgmtGrid Mgmt: $11,034$11,034LoadLoad: $111,041$111,041Power ResourcesPower Resources: $164,602$164,602
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)3,263,271$111,041$03.40¢$111,041
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,627,435$51,699-$62,106-0.64¢-$10,407
Generation — LEC618,627$97,033-$32,08210.50¢$64,951
Generation — Astoria301,020$19,459-$4,0895.11¢$15,371
Generation — Whitney Point276,126$16,172-$3,5974.55¢$12,575
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)592,585$17,316-$8,3901.51¢$8,926
Supplemental0-$784$0—-$784

RD108RD108

Metered load

2.8M kWh

vs 2.9M kWh budget

Total cost

$0.46M

vs $0.57M budget

Cost per kWh (w/o P3 or C&I)

16.22¢

vs 19.57¢ budget

Load covered by resource

103.7%

owned + contracted

1a

Monthly load, kWh

RD108

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.14M0.28M0.42M0.56M0.70Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.06M kWhFeb — 2025 actual: 0.02M kWhMar — 2025 actual: 0.03M kWhApr — 2025 actual: 0.07M kWhMay — 2025 actual: 0.36M kWhJun — 2025 actual: 0.53M kWhJul — 2025 actual: 0.52M kWhAug — 2025 actual: 0.53M kWhSep — 2025 actual: 0.17M kWhOct — 2025 actual: 0.06M kWhNov — 2025 actual: 0.16M kWhDec — 2025 actual: 0.15M kWhJan — 2026 budget: 0.03M kWhFeb — 2026 budget: 0.02M kWhMar — 2026 budget: 0.05M kWhApr — 2026 budget: 0.07M kWhMay — 2026 budget: 0.43M kWhJun — 2026 budget: 0.51M kWhJul — 2026 budget: 0.63M kWhAug — 2026 budget: 0.59M kWhSep — 2026 budget: 0.17M kWhOct — 2026 budget: 0.13M kWhNov — 2026 budget: 0.16M kWhDec — 2026 budget: 0.11M kWhJan — 2026 actual: 0.03M kWhFeb — 2026 actual: 0.02M kWhMar — 2026 actual: 0.05M kWhApr — 2026 actual: 0.07M kWhMay — 2026 actual: 0.41M kWhJun — 2026 actual: 0.49M kWhJul — 2026 actual: 0.61M kWhAug — 2026 actual: 0.57M kWhSep — 2026 actual (estimated): 0.21M kWhOct — 2026 actual (estimated): 0.13M kWhNov — 2026 actual (estimated): 0.16M kWhDec — 2026 actual (estimated): 0.11M kWh
1b

Resource mix

3.1M kWh owned + contracted
Base Resource: 1.33M kWh (43.5%)Generation - Slate (PV+BESS): 0.71M kWh (23.3%)Generation - Whitney Point: 0.69M kWh (22.5%)Generation - LEC: 0.33M kWh (10.7%)3.1MkWh total
ResourceEnergyShare
Base Resource1.33M43.5%
Generation - Slate (PV+BESS)0.71M23.3%
Generation - Whitney Point0.69M22.5%
Generation - LEC0.33M10.7%
1c

Cost composition

Gross total $0.53M

Gross costs before resource credits and allocated overheads, so this totals $0.53M rather than the $0.46M net figure in the KPI row above.

OverheadOverhead: $63,960$63,960DistributionDistribution: $144,404$144,404TransmissionTransmission: $56,666$56,666Grid MgmtGrid Mgmt: $11,916$11,916LoadLoad: $101,656$101,656Power ResourcesPower Resources: $153,900$153,900
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)2,955,393$101,656$03.44¢$101,656
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,332,432$41,875-$50,007-0.61¢-$8,132
Generation — LEC328,683$51,555-$17,04610.50¢$34,509
Generation — Astoria0$0$0—$0
Generation — Whitney Point690,467$40,438-$8,9944.55¢$31,444
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)713,363$41,394-$15,9893.56¢$25,405
Supplemental0-$642$0—-$642

Santa Clara Valley WDSCV

Metered load

20.3M kWh

vs 20.9M kWh budget

Total cost

$2.35M

vs $2.97M budget

Cost per kWh (w/o P3 or C&I)

11.55¢

vs 14.24¢ budget

Load covered by resource

74.5%

owned + contracted

1a

Monthly load, kWh

Santa Clara Valley WD

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.60M1.20M1.80M2.40M3.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 1.29M kWhFeb — 2025 actual: 1.19M kWhMar — 2025 actual: 1.33M kWhApr — 2025 actual: 1.48M kWhMay — 2025 actual: 1.84M kWhJun — 2025 actual: 2.03M kWhJul — 2025 actual: 2.12M kWhAug — 2025 actual: 2.26M kWhSep — 2025 actual: 2.19M kWhOct — 2025 actual: 2.04M kWhNov — 2025 actual: 1.33M kWhDec — 2025 actual: 1.13M kWhJan — 2026 budget: 1.23M kWhFeb — 2026 budget: 1.22M kWhMar — 2026 budget: 1.58M kWhApr — 2026 budget: 1.64M kWhMay — 2026 budget: 1.92M kWhJun — 2026 budget: 2.03M kWhJul — 2026 budget: 2.17M kWhAug — 2026 budget: 2.16M kWhSep — 2026 budget: 2.12M kWhOct — 2026 budget: 1.96M kWhNov — 2026 budget: 1.54M kWhDec — 2026 budget: 1.32M kWhJan — 2026 actual: 1.21M kWhFeb — 2026 actual: 1.19M kWhMar — 2026 actual: 1.55M kWhApr — 2026 actual: 1.61M kWhMay — 2026 actual: 1.89M kWhJun — 2026 actual: 1.99M kWhJul — 2026 actual: 2.12M kWhAug — 2026 actual: 2.11M kWhSep — 2026 actual (estimated): 1.96M kWhOct — 2026 actual (estimated): 1.92M kWhNov — 2026 actual (estimated): 1.50M kWhDec — 2026 actual (estimated): 1.28M kWh
1b

Resource mix

15.5M kWh owned + contracted
Base Resource: 7.85M kWh (50.6%)Generation - Slate (PV+BESS): 3.56M kWh (23.0%)Generation - Whitney Point: 2.07M kWh (13.4%)Generation - Astoria: 1.07M kWh (6.9%)Generation - LEC: 0.94M kWh (6.1%)15.5MkWh total
ResourceEnergyShare
Base Resource7.85M50.6%
Generation - Slate (PV+BESS)3.56M23.0%
Generation - Whitney Point2.07M13.4%
Generation - Astoria1.07M6.9%
Generation - LEC0.94M6.1%
1c

Cost composition

Gross total $2.75M

Gross costs before resource credits and allocated overheads, so this totals $2.75M rather than the $2.35M net figure in the KPI row above.

OverheadOverhead: $121,380$121,380DistributionDistribution: $781,315$781,315TransmissionTransmission: $279,118$279,118Grid MgmtGrid Mgmt: $50,284$50,284LoadLoad: $729,511$729,511Power ResourcesPower Resources: $786,098$786,098
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)20,799,843$729,511$03.51¢$729,511
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource7,846,024$266,597-$305,235-0.49¢-$38,637
Generation — LEC944,418$148,134-$48,97810.50¢$99,156
Generation — Astoria1,069,920$69,165-$14,5335.11¢$54,632
Generation — Whitney Point2,071,097$121,297-$26,9784.55¢$94,318
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)3,561,336$145,158-$62,2162.33¢$82,942
Supplemental0$96,226$0—$96,226

Sonoma County WASCWA

Metered load

34.4M kWh

vs 34.9M kWh budget

Total cost

$3.34M

vs $4.80M budget

Cost per kWh (w/o P3 or C&I)

9.72¢

vs 13.74¢ budget

Load covered by resource

74.8%

owned + contracted

1a

Monthly load, kWh

Sonoma County WA

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M1.00M2.00M3.00M4.00M5.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 2.14M kWhFeb — 2025 actual: 1.90M kWhMar — 2025 actual: 1.95M kWhApr — 2025 actual: 2.14M kWhMay — 2025 actual: 3.02M kWhJun — 2025 actual: 3.66M kWhJul — 2025 actual: 4.00M kWhAug — 2025 actual: 4.03M kWhSep — 2025 actual: 3.46M kWhOct — 2025 actual: 2.71M kWhNov — 2025 actual: 2.27M kWhDec — 2025 actual: 2.32M kWhJan — 2026 budget: 2.13M kWhFeb — 2026 budget: 1.87M kWhMar — 2026 budget: 2.40M kWhApr — 2026 budget: 2.42M kWhMay — 2026 budget: 2.87M kWhJun — 2026 budget: 3.35M kWhJul — 2026 budget: 3.85M kWhAug — 2026 budget: 4.00M kWhSep — 2026 budget: 3.62M kWhOct — 2026 budget: 3.30M kWhNov — 2026 budget: 2.71M kWhDec — 2026 budget: 2.40M kWhJan — 2026 actual: 2.11M kWhFeb — 2026 actual: 1.85M kWhMar — 2026 actual: 2.38M kWhApr — 2026 actual: 2.40M kWhMay — 2026 actual: 2.86M kWhJun — 2026 actual: 3.33M kWhJul — 2026 actual: 3.80M kWhAug — 2026 actual: 3.96M kWhSep — 2026 actual (estimated): 3.42M kWhOct — 2026 actual (estimated): 3.24M kWhNov — 2026 actual (estimated): 2.66M kWhDec — 2026 actual (estimated): 2.35M kWh
1b

Resource mix

26.1M kWh owned + contracted
Base Resource: 13.20M kWh (50.6%)Generation - Whitney Point: 7.73M kWh (29.6%)Generation - Astoria: 2.80M kWh (10.7%)Generation - Slate (PV+BESS): 2.37M kWh (9.1%)26.1MkWh total
ResourceEnergyShare
Base Resource13.20M50.6%
Generation - Whitney Point7.73M29.6%
Generation - Astoria2.80M10.7%
Generation - Slate (PV+BESS)2.37M9.1%
1c

Cost composition

Gross total $4.01M

Gross costs before resource credits and allocated overheads, so this totals $4.01M rather than the $3.34M net figure in the KPI row above.

OverheadOverhead: $168,311$168,311DistributionDistribution: $621,252$621,252TransmissionTransmission: $673,395$673,395Grid MgmtGrid Mgmt: $87,989$87,989LoadLoad: $1,237,998$1,237,998Power ResourcesPower Resources: $1,216,367$1,216,367
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)34,875,151$1,237,998$03.55¢$1,237,998
Specific Projects (BOR + WSH)0$8,953$0—$8,953
Base Resource13,196,376$446,344-$512,496-0.50¢-$66,152
Generation — LEC0$0$0—$0
Generation — Astoria2,795,586$180,720-$37,9725.11¢$142,748
Generation — Whitney Point7,732,438$452,861-$100,7244.55¢$352,138
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)2,371,272$69,288-$33,5851.51¢$35,703
Supplemental0$76,751$0—$76,751

West Stanislaus IDWSID

Metered load

16.3M kWh

vs 19.7M kWh budget

Total cost

$1.48M

vs $2.21M budget

Cost per kWh (w/o P3 or C&I)

9.08¢

vs 11.24¢ budget

Load covered by resource

88.8%

owned + contracted

1a

Monthly load, kWh

West Stanislaus ID

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.80M1.60M2.40M3.20M4.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.08M kWhFeb — 2025 actual: 0.21M kWhMar — 2025 actual: 0.67M kWhApr — 2025 actual: 1.67M kWhMay — 2025 actual: 2.18M kWhJun — 2025 actual: 1.90M kWhJul — 2025 actual: 2.08M kWhAug — 2025 actual: 2.26M kWhSep — 2025 actual: 1.31M kWhOct — 2025 actual: 0.67M kWhNov — 2025 actual: 0.20M kWhDec — 2025 actual: 0.06M kWhJan — 2026 budget: 0.06M kWhFeb — 2026 budget: 0.28M kWhMar — 2026 budget: 1.48M kWhApr — 2026 budget: 2.48M kWhMay — 2026 budget: 3.15M kWhJun — 2026 budget: 2.40M kWhJul — 2026 budget: 2.56M kWhAug — 2026 budget: 3.91M kWhSep — 2026 budget: 1.37M kWhOct — 2026 budget: 1.10M kWhNov — 2026 budget: 0.58M kWhDec — 2026 budget: 0.34M kWhJan — 2026 actual: 0.06M kWhFeb — 2026 actual: 0.27M kWhMar — 2026 actual: 1.46M kWhApr — 2026 actual: 2.43M kWhMay — 2026 actual: 3.09M kWhJun — 2026 actual: 2.40M kWhJul — 2026 actual: 2.51M kWhAug — 2026 actual: 2.15M kWhSep — 2026 actual (estimated): 0.00M kWhOct — 2026 actual (estimated): 1.08M kWhNov — 2026 actual (estimated): 0.57M kWhDec — 2026 actual (estimated): 0.33M kWh
1b

Resource mix

14.7M kWh owned + contracted
Base Resource: 9.21M kWh (62.6%)Generation - Slate (PV+BESS): 4.75M kWh (32.3%)Generation - LEC: 0.74M kWh (5.0%)14.7MkWh total
ResourceEnergyShare
Base Resource9.21M62.6%
Generation - Slate (PV+BESS)4.75M32.3%
Generation - LEC0.74M5.0%
1c

Cost composition

Gross total $1.88M

Gross costs before resource credits and allocated overheads, so this totals $1.88M rather than the $1.48M net figure in the KPI row above.

OverheadOverhead: $91,727$91,727DistributionDistribution: $536,676$536,676TransmissionTransmission: $165,415$165,415Grid MgmtGrid Mgmt: $56,582$56,582LoadLoad: $474,475$474,475Power ResourcesPower Resources: $550,962$550,962
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)16,550,665$474,475$02.87¢$474,475
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource9,208,282$270,294-$313,762-0.47¢-$43,469
Generation — LEC738,533$115,841-$38,30110.50¢$77,540
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)4,751,401$221,029-$90,8472.74¢$130,182
Supplemental0-$4,422$0—-$4,422

Westlands WDWWD

Metered load

88.9M kWh

vs 93.9M kWh budget

Total cost

$12.98M

vs $19.61M budget

Cost per kWh (w/o P3 or C&I)

14.59¢

vs 20.88¢ budget

Load covered by resource

127.1%

owned + contracted

1a

Monthly load, kWh

Westlands WD

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M4.00M8.00M12.00M16.00M20.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.85M kWhFeb — 2025 actual: 1.54M kWhMar — 2025 actual: 1.01M kWhApr — 2025 actual: 2.91M kWhMay — 2025 actual: 5.06M kWhJun — 2025 actual: 5.93M kWhJul — 2025 actual: 5.76M kWhAug — 2025 actual: 3.64M kWhSep — 2025 actual: 2.09M kWhOct — 2025 actual: 1.59M kWhNov — 2025 actual: 0.39M kWhDec — 2025 actual: 0.46M kWhJan — 2026 budget: 0.70M kWhFeb — 2026 budget: 1.31M kWhMar — 2026 budget: 3.87M kWhApr — 2026 budget: 12.00M kWhMay — 2026 budget: 16.18M kWhJun — 2026 budget: 17.05M kWhJul — 2026 budget: 17.36M kWhAug — 2026 budget: 10.60M kWhSep — 2026 budget: 5.20M kWhOct — 2026 budget: 4.72M kWhNov — 2026 budget: 2.49M kWhDec — 2026 budget: 2.43M kWhJan — 2026 actual: 0.66M kWhFeb — 2026 actual: 1.23M kWhMar — 2026 actual: 3.63M kWhApr — 2026 actual: 11.25M kWhMay — 2026 actual: 15.56M kWhJun — 2026 actual: 16.00M kWhJul — 2026 actual: 16.34M kWhAug — 2026 actual: 10.39M kWhSep — 2026 actual (estimated): 4.74M kWhOct — 2026 actual (estimated): 4.45M kWhNov — 2026 actual (estimated): 2.35M kWhDec — 2026 actual (estimated): 2.30M kWh
1b

Resource mix

120.8M kWh owned + contracted
Base Resource: 74.17M kWh (61.4%)District Specific Projects (BOR + WSH): 9.99M kWh (8.3%)Generation - Slate (PV+BESS): 9.51M kWh (7.9%)Generation - Astoria: 9.23M kWh (7.6%)Generation - Whitney Point: 8.28M kWh (6.9%)Generation - Luna Valley: 5.31M kWh (4.4%)Generation - LEC: 4.27M kWh (3.5%)120.8MkWh total
ResourceEnergyShare
Base Resource74.17M61.4%
District Specific Projects (BOR + WSH)9.99M8.3%
Generation - Slate (PV+BESS)9.51M7.9%
Generation - Astoria9.23M7.6%
Generation - Whitney Point8.28M6.9%
Generation - Luna Valley5.31M4.4%
Generation - LEC4.27M3.5%
1c

Cost composition

Gross total $16.02M

Gross costs before resource credits and allocated overheads, so this totals $16.02M rather than the $12.98M net figure in the KPI row above.

OverheadOverhead: $880,961$880,961DistributionDistribution: $5,969,924$5,969,924TransmissionTransmission: $1,887,829$1,887,829Grid MgmtGrid Mgmt: $334,063$334,063LoadLoad: $2,792,300$2,792,300Power ResourcesPower Resources: $4,150,876$4,150,876
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)95,000,011$2,792,300$02.94¢$2,792,300
Specific Projects (BOR + WSH)9,992,000$17,010-$171,795-1.55¢-$154,785
Base Resource74,165,098$2,081,149-$2,499,918-0.56¢-$418,768
Generation — LEC4,272,175$670,087-$221,55710.50¢$448,530
Generation — Astoria9,227,507$596,512-$125,3375.11¢$471,175
Generation — Whitney Point8,284,690$485,205-$107,9184.55¢$377,287
Generation — Luna Valley5,314,764$112,898-$29,7621.56¢$83,136
Generation — Slate (PV+BESS)9,514,549$541,033-$210,1383.48¢$330,895
Supplemental0-$26,784$0—-$26,784

Zone 7 WAZ7

Metered load

4.4M kWh

vs 4.8M kWh budget

Total cost

$0.62M

vs $1.02M budget

Cost per kWh (w/o P3 or C&I)

13.99¢

vs 21.09¢ budget

Load covered by resource

80.2%

owned + contracted

1a

Monthly load, kWh

Zone 7 WA

Aug is the last actual month. September–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.14M0.28M0.42M0.56M0.70Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.32M kWhFeb — 2025 actual: 0.29M kWhMar — 2025 actual: 0.34M kWhApr — 2025 actual: 0.47M kWhMay — 2025 actual: 0.44M kWhJun — 2025 actual: 0.41M kWhJul — 2025 actual: 0.45M kWhAug — 2025 actual: 0.45M kWhSep — 2025 actual: 0.55M kWhOct — 2025 actual: 0.30M kWhNov — 2025 actual: 0.25M kWhDec — 2025 actual: 0.27M kWhJan — 2026 budget: 0.22M kWhFeb — 2026 budget: 0.21M kWhMar — 2026 budget: 0.36M kWhApr — 2026 budget: 0.35M kWhMay — 2026 budget: 0.32M kWhJun — 2026 budget: 0.36M kWhJul — 2026 budget: 0.40M kWhAug — 2026 budget: 0.36M kWhSep — 2026 budget: 0.63M kWhOct — 2026 budget: 0.63M kWhNov — 2026 budget: 0.60M kWhDec — 2026 budget: 0.39M kWhJan — 2026 actual: 0.22M kWhFeb — 2026 actual: 0.21M kWhMar — 2026 actual: 0.36M kWhApr — 2026 actual: 0.34M kWhMay — 2026 actual: 0.31M kWhJun — 2026 actual: 0.35M kWhJul — 2026 actual: 0.39M kWhAug — 2026 actual: 0.35M kWhSep — 2026 actual (estimated): 0.28M kWhOct — 2026 actual (estimated): 0.62M kWhNov — 2026 actual (estimated): 0.59M kWhDec — 2026 actual (estimated): 0.39M kWh
1b

Resource mix

3.6M kWh owned + contracted
Base Resource: 1.48M kWh (40.8%)Generation - Slate (PV+BESS): 1.19M kWh (32.8%)Generation - Whitney Point: 0.55M kWh (15.3%)Generation - Astoria: 0.40M kWh (11.1%)3.6MkWh total
ResourceEnergyShare
Base Resource1.48M40.8%
Generation - Slate (PV+BESS)1.19M32.8%
Generation - Whitney Point0.55M15.3%
Generation - Astoria0.40M11.1%
1c

Cost composition

Gross total $0.70M

Gross costs before resource credits and allocated overheads, so this totals $0.70M rather than the $0.62M net figure in the KPI row above.

OverheadOverhead: $75,614$75,614DistributionDistribution: $236,883$236,883TransmissionTransmission: $57,657$57,657Grid MgmtGrid Mgmt: $10,519$10,519LoadLoad: $166,768$166,768Power ResourcesPower Resources: $156,402$156,402
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)4,503,447$166,768$03.70¢$166,768
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,475,538$51,178-$58,953-0.53¢-$7,775
Generation — LEC0$0$0—$0
Generation — Astoria400,863$25,914-$5,4455.11¢$20,469
Generation — Whitney Point552,252$32,343-$7,1944.55¢$25,150
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)1,185,170$34,631-$16,7801.51¢$17,852
Supplemental0$13,836$0—$13,836
Authority-wide
2

Funds available as of August 31, 2026

Total $14.48M

Participant-attributable balances only; excludes Board-approved reserves, working capital and CAISO collateral. Bars are scaled to each participant’s own total, so segment widths compare the mix of funds, not the amount — amounts are the dollar figures shown.

P3 available Cap & Invest available Funds on deposit
0%25%50%75%100%Arvin-Edison WSDArvin-Edison WSD — P3 available: $185,714 (33.6%)$185,714Arvin-Edison WSD — Cap & Invest available: $366,700 (66.4%)$366,700$0.55MBanta-Carbona IDBanta-Carbona ID — P3 available: $65,504 (12.5%)$65,504Banta-Carbona ID — Cap & Invest available: $177,163 (33.9%)$177,163Banta-Carbona ID — Funds on deposit: $280,038 (53.6%)$280,038$0.52MByron-Bethany IDByron-Bethany ID — P3 available: $29,112 (33.5%)$29,112Byron-Bethany ID — Funds on deposit: $57,887 (66.5%)$57,887$0.09MCawelo WDCawelo WD — P3 available: $222,954 (22.8%)$222,954Cawelo WD — Cap & Invest available: $252,593 (25.8%)$252,593Cawelo WD — Funds on deposit: $503,490 (51.4%)$503,490$0.98MGlenn-Colusa IDGlenn-Colusa ID — P3 available: $95,892 (44.8%)$95,892Glenn-Colusa ID — Funds on deposit: $118,183 (55.2%)$118,183$0.21MJames IDJames ID — P3 available: $41,123 (13.0%)$41,123James ID — Cap & Invest available: $197,393 (62.4%)$197,393James ID — Funds on deposit: $77,619 (24.6%)$77,619$0.32MLower Tule River IDLower Tule River ID — P3 available: $107,376 (23.9%)$107,376Lower Tule River ID — Cap & Invest available: $159,892 (35.6%)$159,892Lower Tule River ID — Funds on deposit: $181,788 (40.5%)$181,788$0.45MPrinceton Prov IDPrinceton Prov ID — P3 available: $9,369 (8.2%)$9,369Princeton Prov ID — Cap & Invest available: $105,546 (91.8%)$105,546$0.11MRD108RD108 — P3 available: $45,702 (31.4%)$45,702RD108 — Funds on deposit: $100,000 (68.6%)$100,000$0.15MSanta Clara Valley WDSanta Clara Valley WD — P3 available: $112,150 (13.3%)$112,150Santa Clara Valley WD — Cap & Invest available: $210,962 (25.1%)$210,962Santa Clara Valley WD — Funds on deposit: $518,428 (61.6%)$518,428$0.84MSonoma County WASonoma County WA — P3 available: $378,902 (18.3%)$378,902Sonoma County WA — Cap & Invest available: $983,193 (47.6%)$983,193Sonoma County WA — Funds on deposit: $704,570 (34.1%)$704,570$2.07MWest Stanislaus IDWest Stanislaus ID — P3 available: $191,836 (15.8%)$191,836West Stanislaus ID — Cap & Invest available: $742,097 (61.0%)$742,097West Stanislaus ID — Funds on deposit: $282,746 (23.2%)$282,746$1.22MWestlands WDWestlands WD — P3 available: $809,451 (12.4%)$809,451Westlands WD — Cap & Invest available: $5,593,270 (85.6%)$5,593,270Westlands WD — Funds on deposit: $127,894 (2.0%)$127,894$6.53MZone 7 WAZone 7 WA — P3 available: $54,869 (12.5%)$54,869Zone 7 WA — Cap & Invest available: $239,988 (54.5%)$239,988Zone 7 WA — Funds on deposit: $145,637 (33.1%)$145,637$0.44MShare of each participant’s available funds · dollar total at right

Total funds available

$14.48M

P3 available

$2.35M

Cap & Invest available

$9.03M

Funds on deposit

$3.10M

Funds available detail · all 14 participants
Participant P3Cap & InvestOn deposit Total available
Arvin-Edison WSD$185,714$366,700$0$552,414
Banta-Carbona ID$65,504$177,163$280,038$522,705
Byron-Bethany ID$29,112$0$57,887$87,000
Cawelo WD$222,954$252,593$503,490$979,037
Glenn-Colusa ID$95,892$0$118,183$214,076
James ID$41,123$197,393$77,619$316,135
Lower Tule River ID$107,376$159,892$181,788$449,057
Princeton Prov ID$9,369$105,546$0$114,914
RD108$45,702$0$100,000$145,702
Santa Clara Valley WD$112,150$210,962$518,428$841,539
Sonoma County WA$378,902$983,193$704,570$2,066,666
West Stanislaus ID$191,836$742,097$282,746$1,216,679
Westlands WD$809,451$5,593,270$127,894$6,530,614
Zone 7 WA$54,869$239,988$145,637$440,494
3

Business unit activities — August & September 2026

Financial

Board packet financials; vendor payments; coordination with GM on ARB allowance consignments; participate at August Board meeting.

Administrative

Staff coordination; supporting AI implementation across all business units; REC agreement updates; participate at August Board meeting; Board meeting packet preparation for October Board Meeting; 2027 Budget support; Project development support; Participation on WAPA committees.

Compliance

RA policy development.

Operations

Daily operations; developing 2027 budget; participate at August Board meeting; POI additions/terminations; displacement program.

Project Development

Incorporating engineering services in collaborative participation with Project Participants on 7 distributed solar facilities, 2 substations and 3 distribution intervening facilities; POI addition/removal support; aux load meetings on mobile batteries.

Legal

WDT settlement approved by FERC on September 14; PPA and license modifications for distributed solar regarding interconnection status; building conformed copies of all PG&E service agreements and associated WAPA versions; participate at August Board Meeting.