PWRPA Dashboard — September 2026

2026 reconciliation · funds available · business unit activities

Sections 1a–1c: Actual January–September, estimated October–December 2026.

Hover any point or bar for detail · Ctrl/Cmd-P to print
2026 reconciliation

PWRPA — all participantsPWRPA

Metered load

341.2M kWh

vs 333.3M kWh budget

Total cost

$41.68M

vs $56.14M budget

Cost per kWh (w/o P3 or C&I)

12.22¢

vs 16.84¢ budget

Load covered by resource

99.3%

owned + contracted

1a

Monthly load, kWh

PWRPA — all participants

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M12.00M24.00M36.00M48.00M60.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 7.91M kWhFeb — 2025 actual: 8.55M kWhMar — 2025 actual: 12.01M kWhApr — 2025 actual: 22.47M kWhMay — 2025 actual: 35.83M kWhJun — 2025 actual: 41.12M kWhJul — 2025 actual: 39.40M kWhAug — 2025 actual: 34.86M kWhSep — 2025 actual: 25.64M kWhOct — 2025 actual: 17.78M kWhNov — 2025 actual: 9.08M kWhDec — 2025 actual: 7.44M kWhJan — 2026 budget: 12.34M kWhFeb — 2026 budget: 19.08M kWhMar — 2026 budget: 19.51M kWhApr — 2026 budget: 28.15M kWhMay — 2026 budget: 44.31M kWhJun — 2026 budget: 48.64M kWhJul — 2026 budget: 47.74M kWhAug — 2026 budget: 41.08M kWhSep — 2026 budget: 27.67M kWhOct — 2026 budget: 22.79M kWhNov — 2026 budget: 13.29M kWhDec — 2026 budget: 8.73M kWhJan — 2026 actual: 14.08M kWhFeb — 2026 actual: 7.78M kWhMar — 2026 actual: 22.24M kWhApr — 2026 actual: 34.51M kWhMay — 2026 actual: 47.41M kWhJun — 2026 actual: 48.98M kWhJul — 2026 actual: 51.34M kWhAug — 2026 actual: 44.20M kWhSep — 2026 actual: 27.45M kWhOct — 2026 actual (estimated): 20.48M kWhNov — 2026 actual (estimated): 14.17M kWhDec — 2026 actual (estimated): 8.55M kWh
1b

Resource mix

351.7M kWh owned + contracted
Base Resource: 197.86M kWh (56.3%)Generation - Slate (PV+BESS): 62.01M kWh (17.6%)Generation - Whitney Point: 30.84M kWh (8.8%)Generation - Astoria: 27.28M kWh (7.8%)Generation - LEC: 17.38M kWh (4.9%)District Specific Projects (BOR + WSH): 10.05M kWh (2.9%)Generation - Luna Valley: 5.48M kWh (1.6%)Supplemental: 0.74M kWh (0.2%)351.7MkWh total
ResourceEnergyShare
Base Resource197.86M56.3%
Generation - Slate (PV+BESS)62.01M17.6%
Generation - Whitney Point30.84M8.8%
Generation - Astoria27.28M7.8%
Generation - LEC17.38M4.9%
District Specific Projects (BOR + WSH)10.05M2.9%
Generation - Luna Valley5.48M1.6%
Supplemental0.74M0.2%
1c

Cost composition

Gross total $50.70M

Gross costs before resource credits and allocated overheads, so this totals $50.70M rather than the $41.68M net figure in the KPI row above.

OverheadOverhead: $2,364,798$2,364,798DistributionDistribution: $14,303,953$14,303,953TransmissionTransmission: $7,102,804$7,102,804Grid MgmtGrid Mgmt: $1,311,636$1,311,636LoadLoad: $11,245,295$11,245,295Power ResourcesPower Resources: $14,368,025$14,368,025
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)353,984,366$11,245,295$03.18¢$11,245,295
Specific Projects (BOR + WSH)10,052,000$26,174-$160,930-1.34¢-$134,756
Base Resource197,863,319$6,212,945-$7,009,113-0.40¢-$796,167
Generation — LEC17,381,337$2,699,587-$933,22110.16¢$1,766,366
Generation — Astoria27,282,565$1,707,591-$372,0254.90¢$1,335,565
Generation — Whitney Point30,843,987$1,801,974-$395,9244.56¢$1,406,050
Generation — Luna Valley5,477,582$113,377-$27,6991.56¢$85,678
Generation — Slate (PV+BESS)62,013,231$2,619,064-$1,150,8422.37¢$1,468,222
Supplemental744,000$244,257-$25,41129.41¢$218,846

Arvin-Edison WSDAEWSD

Metered load

109.6M kWh

vs 94.8M kWh budget

Total cost

$12.57M

vs $15.64M budget

Cost per kWh (w/o P3 or C&I)

11.48¢

vs 16.49¢ budget

Load covered by resource

95.6%

owned + contracted

1a

Monthly load, kWh

Arvin-Edison WSD

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M4.00M8.00M12.00M16.00M20.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 2.62M kWhFeb — 2025 actual: 2.42M kWhMar — 2025 actual: 4.29M kWhApr — 2025 actual: 8.64M kWhMay — 2025 actual: 14.24M kWhJun — 2025 actual: 16.01M kWhJul — 2025 actual: 14.06M kWhAug — 2025 actual: 13.57M kWhSep — 2025 actual: 11.39M kWhOct — 2025 actual: 7.14M kWhNov — 2025 actual: 2.03M kWhDec — 2025 actual: 0.64M kWhJan — 2026 budget: 2.42M kWhFeb — 2026 budget: 4.17M kWhMar — 2026 budget: 6.08M kWhApr — 2026 budget: 7.85M kWhMay — 2026 budget: 11.46M kWhJun — 2026 budget: 13.83M kWhJul — 2026 budget: 14.35M kWhAug — 2026 budget: 13.35M kWhSep — 2026 budget: 9.97M kWhOct — 2026 budget: 7.32M kWhNov — 2026 budget: 3.25M kWhDec — 2026 budget: 0.77M kWhJan — 2026 actual: 8.60M kWhFeb — 2026 actual: 1.65M kWhMar — 2026 actual: 8.63M kWhApr — 2026 actual: 11.64M kWhMay — 2026 actual: 13.63M kWhJun — 2026 actual: 14.14M kWhJul — 2026 actual: 14.58M kWhAug — 2026 actual: 15.50M kWhSep — 2026 actual: 9.99M kWhOct — 2026 actual (estimated): 6.47M kWhNov — 2026 actual (estimated): 4.13M kWhDec — 2026 actual (estimated): 0.59M kWh
1b

Resource mix

108.4M kWh owned + contracted
Base Resource: 62.54M kWh (57.7%)Generation - Slate (PV+BESS): 21.44M kWh (19.8%)Generation - Astoria: 10.46M kWh (9.7%)Generation - Whitney Point: 9.81M kWh (9.1%)Generation - LEC: 4.11M kWh (3.8%)108.4MkWh total
ResourceEnergyShare
Base Resource62.54M57.7%
Generation - Slate (PV+BESS)21.44M19.8%
Generation - Astoria10.46M9.7%
Generation - Whitney Point9.81M9.1%
Generation - LEC4.11M3.8%
1c

Cost composition

Gross total $15.37M

Gross costs before resource credits and allocated overheads, so this totals $15.37M rather than the $12.57M net figure in the KPI row above.

OverheadOverhead: $406,789$406,789DistributionDistribution: $4,141,960$4,141,960TransmissionTransmission: $2,443,281$2,443,281Grid MgmtGrid Mgmt: $401,867$401,867LoadLoad: $3,616,879$3,616,879Power ResourcesPower Resources: $4,357,498$4,357,498
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)113,356,391$3,616,879$03.19¢$3,616,879
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource62,542,931$1,986,840-$2,215,675-0.37¢-$228,834
Generation — LEC4,112,200$638,690-$220,78810.16¢$417,901
Generation — Astoria10,461,793$654,794-$142,6574.90¢$512,137
Generation — Whitney Point9,813,940$573,352-$125,9754.56¢$447,377
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)21,442,593$703,187-$340,3351.69¢$362,852
Supplemental0$50,930$0—$50,930

Banta-Carbona IDBCID

Metered load

17.5M kWh

vs 17.6M kWh budget

Total cost

$1.38M

vs $2.06M budget

Cost per kWh (w/o P3 or C&I)

7.86¢

vs 11.72¢ budget

Load covered by resource

86.7%

owned + contracted

1a

Monthly load, kWh

Banta-Carbona ID

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.80M1.60M2.40M3.20M4.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.02M kWhFeb — 2025 actual: 0.58M kWhMar — 2025 actual: 1.28M kWhApr — 2025 actual: 1.81M kWhMay — 2025 actual: 2.56M kWhJun — 2025 actual: 2.59M kWhJul — 2025 actual: 1.81M kWhAug — 2025 actual: 1.43M kWhSep — 2025 actual: 0.99M kWhOct — 2025 actual: 0.43M kWhNov — 2025 actual: 0.91M kWhDec — 2025 actual: 1.28M kWhJan — 2026 budget: 1.00M kWhFeb — 2026 budget: 1.00M kWhMar — 2026 budget: 1.50M kWhApr — 2026 budget: 2.00M kWhMay — 2026 budget: 2.60M kWhJun — 2026 budget: 2.70M kWhJul — 2026 budget: 2.20M kWhAug — 2026 budget: 2.00M kWhSep — 2026 budget: 1.50M kWhOct — 2026 budget: 1.00M kWhNov — 2026 budget: 0.05M kWhDec — 2026 budget: 0.05M kWhJan — 2026 actual: 0.76M kWhFeb — 2026 actual: 1.01M kWhMar — 2026 actual: 2.19M kWhApr — 2026 actual: 2.12M kWhMay — 2026 actual: 3.03M kWhJun — 2026 actual: 2.54M kWhJul — 2026 actual: 2.15M kWhAug — 2026 actual: 1.51M kWhSep — 2026 actual: 1.15M kWhOct — 2026 actual (estimated): 0.97M kWhNov — 2026 actual (estimated): 0.05M kWhDec — 2026 actual (estimated): 0.05M kWh
1b

Resource mix

15.2M kWh owned + contracted
Base Resource: 8.16M kWh (53.6%)Generation - Slate (PV+BESS): 4.78M kWh (31.4%)Generation - LEC: 1.55M kWh (10.2%)Supplemental: 0.74M kWh (4.9%)15.2MkWh total
ResourceEnergyShare
Base Resource8.16M53.6%
Generation - Slate (PV+BESS)4.78M31.4%
Generation - LEC1.55M10.2%
Supplemental0.74M4.9%
1c

Cost composition

Gross total $1.79M

Gross costs before resource credits and allocated overheads, so this totals $1.79M rather than the $1.38M net figure in the KPI row above.

OverheadOverhead: $98,532$98,532DistributionDistribution: $0$0TransmissionTransmission: $402,806$402,806Grid MgmtGrid Mgmt: $49,069$49,069LoadLoad: $488,489$488,489Power ResourcesPower Resources: $754,478$754,478
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)17,569,689$488,489$02.78¢$488,489
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource8,159,017$256,002-$275,738-0.24¢-$19,736
Generation — LEC1,546,509$240,197-$83,03410.16¢$157,164
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)4,782,259$303,179-$117,5503.88¢$185,629
Supplemental744,000$42,871-$25,4112.35¢$17,460

Byron-Bethany IDBBID

Metered load

2.6M kWh

vs 2.8M kWh budget

Total cost

$0.37M

vs $0.55M budget

Cost per kWh (w/o P3 or C&I)

14.51¢

vs 19.70¢ budget

Load covered by resource

136.6%

owned + contracted

1a

Monthly load, kWh

Byron-Bethany ID

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.10M0.20M0.30M0.40M0.50Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.02M kWhFeb — 2025 actual: 0.01M kWhMar — 2025 actual: 0.16M kWhApr — 2025 actual: 0.37M kWhMay — 2025 actual: 0.22M kWhJun — 2025 actual: 0.00M kWhJul — 2025 actual: 0.00M kWhAug — 2025 actual: 0.00M kWhSep — 2025 actual: 0.16M kWhOct — 2025 actual: 0.31M kWhNov — 2025 actual: 0.01M kWhDec — 2025 actual: 0.00M kWhJan — 2026 budget: 0.01M kWhFeb — 2026 budget: 0.01M kWhMar — 2026 budget: 0.05M kWhApr — 2026 budget: 0.28M kWhMay — 2026 budget: 0.41M kWhJun — 2026 budget: 0.49M kWhJul — 2026 budget: 0.47M kWhAug — 2026 budget: 0.39M kWhSep — 2026 budget: 0.32M kWhOct — 2026 budget: 0.27M kWhNov — 2026 budget: 0.06M kWhDec — 2026 budget: 0.03M kWhJan — 2026 actual: 0.00M kWhFeb — 2026 actual: 0.00M kWhMar — 2026 actual: 0.24M kWhApr — 2026 actual: 0.31M kWhMay — 2026 actual: 0.39M kWhJun — 2026 actual: 0.45M kWhJul — 2026 actual: 0.42M kWhAug — 2026 actual: 0.36M kWhSep — 2026 actual: 0.31M kWhOct — 2026 actual (estimated): 0.00M kWhNov — 2026 actual (estimated): 0.06M kWhDec — 2026 actual (estimated): 0.03M kWh
1b

Resource mix

3.6M kWh owned + contracted
Base Resource: 2.11M kWh (59.4%)Generation - LEC: 0.73M kWh (20.5%)Generation - Slate (PV+BESS): 0.72M kWh (20.1%)3.6MkWh total
ResourceEnergyShare
Base Resource2.11M59.4%
Generation - LEC0.73M20.5%
Generation - Slate (PV+BESS)0.72M20.1%
1c

Cost composition

Gross total $0.46M

Gross costs before resource credits and allocated overheads, so this totals $0.46M rather than the $0.37M net figure in the KPI row above.

OverheadOverhead: $61,152$61,152DistributionDistribution: $95,640$95,640TransmissionTransmission: $51,788$51,788Grid MgmtGrid Mgmt: $10,485$10,485LoadLoad: $78,141$78,141Power ResourcesPower Resources: $165,814$165,814
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)2,605,653$78,141$03.00¢$78,141
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource2,114,844$58,082-$73,817-0.74¢-$15,735
Generation — LEC728,880$113,207-$39,13410.16¢$74,072
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)715,697$33,076-$14,0902.65¢$18,986
Supplemental0-$1,022$0—-$1,022

Cawelo WDCWD

Metered load

17.5M kWh

vs 14.1M kWh budget

Total cost

$2.18M

vs $2.58M budget

Cost per kWh (w/o P3 or C&I)

12.49¢

vs 18.29¢ budget

Load covered by resource

98.5%

owned + contracted

1a

Monthly load, kWh

Cawelo WD

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.80M1.60M2.40M3.20M4.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.02M kWhFeb — 2025 actual: 0.05M kWhMar — 2025 actual: 0.47M kWhApr — 2025 actual: 1.32M kWhMay — 2025 actual: 1.96M kWhJun — 2025 actual: 3.39M kWhJul — 2025 actual: 3.84M kWhAug — 2025 actual: 3.32M kWhSep — 2025 actual: 1.96M kWhOct — 2025 actual: 0.84M kWhNov — 2025 actual: 0.03M kWhDec — 2025 actual: 0.03M kWhJan — 2026 budget: 0.03M kWhFeb — 2026 budget: 0.59M kWhMar — 2026 budget: 0.34M kWhApr — 2026 budget: 0.60M kWhMay — 2026 budget: 1.64M kWhJun — 2026 budget: 2.52M kWhJul — 2026 budget: 3.24M kWhAug — 2026 budget: 2.84M kWhSep — 2026 budget: 1.33M kWhOct — 2026 budget: 0.62M kWhNov — 2026 budget: 0.25M kWhDec — 2026 budget: 0.08M kWhJan — 2026 actual: 0.02M kWhFeb — 2026 actual: 0.03M kWhMar — 2026 actual: 0.89M kWhApr — 2026 actual: 1.12M kWhMay — 2026 actual: 2.43M kWhJun — 2026 actual: 2.83M kWhJul — 2026 actual: 3.63M kWhAug — 2026 actual: 3.51M kWhSep — 2026 actual: 1.68M kWhOct — 2026 actual (estimated): 0.99M kWhNov — 2026 actual (estimated): 0.26M kWhDec — 2026 actual (estimated): 0.08M kWh
1b

Resource mix

17.8M kWh owned + contracted
Generation - Slate (PV+BESS): 9.90M kWh (55.6%)Base Resource: 4.97M kWh (27.9%)Generation - Astoria: 1.63M kWh (9.2%)Generation - LEC: 1.30M kWh (7.3%)17.8MkWh total
ResourceEnergyShare
Generation - Slate (PV+BESS)9.90M55.6%
Base Resource4.97M27.9%
Generation - Astoria1.63M9.2%
Generation - LEC1.30M7.3%
1c

Cost composition

Gross total $2.56M

Gross costs before resource credits and allocated overheads, so this totals $2.56M rather than the $2.18M net figure in the KPI row above.

OverheadOverhead: $92,921$92,921DistributionDistribution: $561,466$561,466TransmissionTransmission: $398,068$398,068Grid MgmtGrid Mgmt: $84,329$84,329LoadLoad: $596,402$596,402Power ResourcesPower Resources: $831,114$831,114
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)18,089,447$596,402$03.30¢$596,402
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource4,974,748$164,959-$179,741-0.30¢-$14,782
Generation — LEC1,301,574$202,155-$69,88310.16¢$132,272
Generation — Astoria1,634,220$102,284-$22,2844.90¢$80,000
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)9,901,322$443,156-$190,8602.55¢$252,296
Supplemental0-$2,446$0—-$2,446

Glenn-Colusa IDGCID

Metered load

11.7M kWh

vs 11.6M kWh budget

Total cost

$1.12M

vs $1.53M budget

Cost per kWh (w/o P3 or C&I)

9.63¢

vs 13.15¢ budget

Load covered by resource

93.2%

owned + contracted

1a

Monthly load, kWh

Glenn-Colusa ID

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.60M1.20M1.80M2.40M3.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.20M kWhFeb — 2025 actual: 0.04M kWhMar — 2025 actual: 0.10M kWhApr — 2025 actual: 0.60M kWhMay — 2025 actual: 2.00M kWhJun — 2025 actual: 2.27M kWhJul — 2025 actual: 2.32M kWhAug — 2025 actual: 1.68M kWhSep — 2025 actual: 0.54M kWhOct — 2025 actual: 0.88M kWhNov — 2025 actual: 1.08M kWhDec — 2025 actual: 0.64M kWhJan — 2026 budget: 0.14M kWhFeb — 2026 budget: 0.09M kWhMar — 2026 budget: 0.12M kWhApr — 2026 budget: 0.54M kWhMay — 2026 budget: 1.89M kWhJun — 2026 budget: 2.17M kWhJul — 2026 budget: 2.50M kWhAug — 2026 budget: 1.73M kWhSep — 2026 budget: 0.49M kWhOct — 2026 budget: 0.69M kWhNov — 2026 budget: 0.75M kWhDec — 2026 budget: 0.50M kWhJan — 2026 actual: 0.04M kWhFeb — 2026 actual: 0.07M kWhMar — 2026 actual: 0.19M kWhApr — 2026 actual: 0.46M kWhMay — 2026 actual: 1.93M kWhJun — 2026 actual: 2.09M kWhJul — 2026 actual: 2.38M kWhAug — 2026 actual: 1.78M kWhSep — 2026 actual: 0.55M kWhOct — 2026 actual (estimated): 0.96M kWhNov — 2026 actual (estimated): 0.74M kWhDec — 2026 actual (estimated): 0.49M kWh
1b

Resource mix

11.0M kWh owned + contracted
Base Resource: 6.65M kWh (60.4%)Generation - Slate (PV+BESS): 1.79M kWh (16.2%)Generation - LEC: 0.87M kWh (7.9%)Generation - Astoria: 0.86M kWh (7.8%)Generation - Whitney Point: 0.84M kWh (7.6%)11.0MkWh total
ResourceEnergyShare
Base Resource6.65M60.4%
Generation - Slate (PV+BESS)1.79M16.2%
Generation - LEC0.87M7.9%
Generation - Astoria0.86M7.8%
Generation - Whitney Point0.84M7.6%
1c

Cost composition

Gross total $1.42M

Gross costs before resource credits and allocated overheads, so this totals $1.42M rather than the $1.12M net figure in the KPI row above.

OverheadOverhead: $93,472$93,472DistributionDistribution: $177,726$177,726TransmissionTransmission: $236,743$236,743Grid MgmtGrid Mgmt: $52,130$52,130LoadLoad: $398,912$398,912Power ResourcesPower Resources: $460,524$460,524
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)11,823,829$398,912$03.37¢$398,912
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource6,652,099$215,423-$247,818-0.49¢-$32,395
Generation — LEC872,710$135,546-$46,85710.16¢$88,689
Generation — Astoria864,587$54,114-$11,7904.90¢$42,324
Generation — Whitney Point841,116$49,140-$10,7974.56¢$38,343
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)1,785,819$51,705-$26,3891.42¢$25,316
Supplemental0$1,275$0—$1,275

James IDJID

Metered load

2.7M kWh

vs 4.1M kWh budget

Total cost

$0.43M

vs $0.69M budget

Cost per kWh (w/o P3 or C&I)

15.60¢

vs 16.68¢ budget

Load covered by resource

111.3%

owned + contracted

1a

Monthly load, kWh

James ID

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.12M0.24M0.36M0.48M0.60Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.04M kWhFeb — 2025 actual: 0.08M kWhMar — 2025 actual: 0.01M kWhApr — 2025 actual: 0.07M kWhMay — 2025 actual: 0.13M kWhJun — 2025 actual: 0.23M kWhJul — 2025 actual: 0.26M kWhAug — 2025 actual: 0.19M kWhSep — 2025 actual: 0.05M kWhOct — 2025 actual: 0.03M kWhNov — 2025 actual: 0.02M kWhDec — 2025 actual: 0.01M kWhJan — 2026 budget: 0.09M kWhFeb — 2026 budget: 0.29M kWhMar — 2026 budget: 0.38M kWhApr — 2026 budget: 0.46M kWhMay — 2026 budget: 0.51M kWhJun — 2026 budget: 0.57M kWhJul — 2026 budget: 0.56M kWhAug — 2026 budget: 0.45M kWhSep — 2026 budget: 0.37M kWhOct — 2026 budget: 0.24M kWhNov — 2026 budget: 0.18M kWhDec — 2026 budget: 0.01M kWhJan — 2026 actual: 0.01M kWhFeb — 2026 actual: 0.05M kWhMar — 2026 actual: 0.12M kWhApr — 2026 actual: 0.03M kWhMay — 2026 actual: 0.27M kWhJun — 2026 actual: 0.49M kWhJul — 2026 actual: 0.45M kWhAug — 2026 actual: 0.31M kWhSep — 2026 actual: 0.41M kWhOct — 2026 actual (estimated): 0.41M kWhNov — 2026 actual (estimated): 0.18M kWhDec — 2026 actual (estimated): 0.01M kWh
1b

Resource mix

3.1M kWh owned + contracted
Base Resource: 1.31M kWh (42.4%)Generation - LEC: 0.69M kWh (22.3%)Generation - Slate (PV+BESS): 0.60M kWh (19.2%)Generation - Whitney Point: 0.28M kWh (9.0%)Generation - Astoria: 0.22M kWh (7.1%)3.1MkWh total
ResourceEnergyShare
Base Resource1.31M42.4%
Generation - LEC0.69M22.3%
Generation - Slate (PV+BESS)0.60M19.2%
Generation - Whitney Point0.28M9.0%
Generation - Astoria0.22M7.1%
1c

Cost composition

Gross total $0.49M

Gross costs before resource credits and allocated overheads, so this totals $0.49M rather than the $0.43M net figure in the KPI row above.

OverheadOverhead: $63,539$63,539DistributionDistribution: $96,649$96,649TransmissionTransmission: $60,205$60,205Grid MgmtGrid Mgmt: $11,374$11,374LoadLoad: $99,198$99,198Power ResourcesPower Resources: $161,941$161,941
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)2,784,332$99,198$03.56¢$99,198
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,314,608$42,513-$49,778-0.55¢-$7,265
Generation — LEC690,068$107,179-$37,05010.16¢$70,128
Generation — Astoria219,892$13,763-$2,9984.90¢$10,764
Generation — Whitney Point280,372$16,380-$3,5994.56¢$12,781
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)595,273$17,235-$8,7961.42¢$8,439
Supplemental0-$643$0—-$643

Lower Tule River IDLTRID

Metered load

9.6M kWh

vs 9.4M kWh budget

Total cost

$1.05M

vs $1.23M budget

Cost per kWh (w/o P3 or C&I)

11.02¢

vs 13.15¢ budget

Load covered by resource

30.4%

owned + contracted

1a

Monthly load, kWh

Lower Tule River ID

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.40M0.80M1.20M1.60M2.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.25M kWhFeb — 2025 actual: 0.22M kWhMar — 2025 actual: 0.37M kWhApr — 2025 actual: 0.58M kWhMay — 2025 actual: 1.01M kWhJun — 2025 actual: 1.27M kWhJul — 2025 actual: 1.46M kWhAug — 2025 actual: 1.12M kWhSep — 2025 actual: 0.73M kWhOct — 2025 actual: 0.40M kWhNov — 2025 actual: 0.13M kWhDec — 2025 actual: 0.28M kWhJan — 2026 budget: 0.31M kWhFeb — 2026 budget: 0.53M kWhMar — 2026 budget: 0.44M kWhApr — 2026 budget: 0.51M kWhMay — 2026 budget: 1.02M kWhJun — 2026 budget: 1.23M kWhJul — 2026 budget: 1.41M kWhAug — 2026 budget: 1.38M kWhSep — 2026 budget: 0.99M kWhOct — 2026 budget: 0.74M kWhNov — 2026 budget: 0.51M kWhDec — 2026 budget: 0.30M kWhJan — 2026 actual: 0.35M kWhFeb — 2026 actual: 0.19M kWhMar — 2026 actual: 0.55M kWhApr — 2026 actual: 0.57M kWhMay — 2026 actual: 1.01M kWhJun — 2026 actual: 1.33M kWhJul — 2026 actual: 1.48M kWhAug — 2026 actual: 1.37M kWhSep — 2026 actual: 0.99M kWhOct — 2026 actual (estimated): 0.89M kWhNov — 2026 actual (estimated): 0.51M kWhDec — 2026 actual (estimated): 0.31M kWh
1b

Resource mix

3.1M kWh owned + contracted
Base Resource: 3.10M kWh (100.0%)3.1MkWh total
ResourceEnergyShare
Base Resource3.10M100.0%
1c

Cost composition

Gross total $1.17M

Gross costs before resource credits and allocated overheads, so this totals $1.17M rather than the $1.05M net figure in the KPI row above.

OverheadOverhead: $77,549$77,549DistributionDistribution: $371,381$371,381TransmissionTransmission: $218,137$218,137Grid MgmtGrid Mgmt: $39,989$39,989LoadLoad: $359,328$359,328Power ResourcesPower Resources: $103,133$103,133
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)10,185,157$359,328$03.53¢$359,328
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource3,095,239$105,288-$116,795-0.37¢-$11,507
Generation — LEC0$0$0—$0
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)0$0$0—$0
Supplemental0-$1,524$0—-$1,524

Princeton Prov IDPPID

Metered load

3.0M kWh

vs 4.3M kWh budget

Total cost

$0.43M

vs $0.68M budget

Cost per kWh (w/o P3 or C&I)

14.28¢

vs 15.86¢ budget

Load covered by resource

113.4%

owned + contracted

1a

Monthly load, kWh

Princeton Prov ID

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.18M0.36M0.54M0.72M0.90Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.01M kWhFeb — 2025 actual: 0.01M kWhMar — 2025 actual: 0.01M kWhApr — 2025 actual: 0.33M kWhMay — 2025 actual: 0.81M kWhJun — 2025 actual: 0.88M kWhJul — 2025 actual: 0.73M kWhAug — 2025 actual: 0.39M kWhSep — 2025 actual: 0.04M kWhOct — 2025 actual: 0.36M kWhNov — 2025 actual: 0.26M kWhDec — 2025 actual: 0.16M kWhJan — 2026 budget: 0.01M kWhFeb — 2026 budget: 0.01M kWhMar — 2026 budget: 0.01M kWhApr — 2026 budget: 0.14M kWhMay — 2026 budget: 0.82M kWhJun — 2026 budget: 0.85M kWhJul — 2026 budget: 0.78M kWhAug — 2026 budget: 0.42M kWhSep — 2026 budget: 0.06M kWhOct — 2026 budget: 0.50M kWhNov — 2026 budget: 0.42M kWhDec — 2026 budget: 0.25M kWhJan — 2026 actual: 0.00M kWhFeb — 2026 actual: 0.00M kWhMar — 2026 actual: 0.00M kWhApr — 2026 actual: 0.16M kWhMay — 2026 actual: 0.60M kWhJun — 2026 actual: 0.56M kWhJul — 2026 actual: 0.46M kWhAug — 2026 actual: 0.21M kWhSep — 2026 actual: 0.01M kWhOct — 2026 actual (estimated): 0.28M kWhNov — 2026 actual (estimated): 0.42M kWhDec — 2026 actual (estimated): 0.25M kWh
1b

Resource mix

3.5M kWh owned + contracted
Base Resource: 1.54M kWh (44.6%)Generation - LEC: 0.73M kWh (21.1%)Generation - Slate (PV+BESS): 0.60M kWh (17.3%)Generation - Astoria: 0.31M kWh (8.9%)Generation - Whitney Point: 0.28M kWh (8.1%)3.5MkWh total
ResourceEnergyShare
Base Resource1.54M44.6%
Generation - LEC0.73M21.1%
Generation - Slate (PV+BESS)0.60M17.3%
Generation - Astoria0.31M8.9%
Generation - Whitney Point0.28M8.1%
1c

Cost composition

Gross total $0.50M

Gross costs before resource credits and allocated overheads, so this totals $0.50M rather than the $0.43M net figure in the KPI row above.

OverheadOverhead: $62,957$62,957DistributionDistribution: $118,238$118,238TransmissionTransmission: $27,549$27,549Grid MgmtGrid Mgmt: $12,689$12,689LoadLoad: $101,969$101,969Power ResourcesPower Resources: $179,086$179,086
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)3,042,104$101,969$03.35¢$101,969
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,538,420$50,252-$57,770-0.49¢-$7,518
Generation — LEC728,602$113,163-$39,11910.16¢$74,044
Generation — Astoria307,733$19,261-$4,1964.90¢$15,064
Generation — Whitney Point280,372$16,380-$3,5994.56¢$12,781
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)595,273$17,235-$8,7961.42¢$8,439
Supplemental0-$754$0—-$754

RD108RD108

Metered load

2.8M kWh

vs 2.7M kWh budget

Total cost

$0.48M

vs $0.57M budget

Cost per kWh (w/o P3 or C&I)

16.93¢

vs 20.80¢ budget

Load covered by resource

106.6%

owned + contracted

1a

Monthly load, kWh

RD108

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.14M0.28M0.42M0.56M0.70Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.06M kWhFeb — 2025 actual: 0.02M kWhMar — 2025 actual: 0.03M kWhApr — 2025 actual: 0.07M kWhMay — 2025 actual: 0.36M kWhJun — 2025 actual: 0.53M kWhJul — 2025 actual: 0.52M kWhAug — 2025 actual: 0.53M kWhSep — 2025 actual: 0.17M kWhOct — 2025 actual: 0.06M kWhNov — 2025 actual: 0.16M kWhDec — 2025 actual: 0.15M kWhJan — 2026 budget: 0.05M kWhFeb — 2026 budget: 0.04M kWhMar — 2026 budget: 0.06M kWhApr — 2026 budget: 0.11M kWhMay — 2026 budget: 0.35M kWhJun — 2026 budget: 0.48M kWhJul — 2026 budget: 0.61M kWhAug — 2026 budget: 0.48M kWhSep — 2026 budget: 0.16M kWhOct — 2026 budget: 0.13M kWhNov — 2026 budget: 0.16M kWhDec — 2026 budget: 0.11M kWhJan — 2026 actual: 0.03M kWhFeb — 2026 actual: 0.02M kWhMar — 2026 actual: 0.05M kWhApr — 2026 actual: 0.07M kWhMay — 2026 actual: 0.41M kWhJun — 2026 actual: 0.49M kWhJul — 2026 actual: 0.61M kWhAug — 2026 actual: 0.57M kWhSep — 2026 actual: 0.21M kWhOct — 2026 actual (estimated): 0.10M kWhNov — 2026 actual (estimated): 0.16M kWhDec — 2026 actual (estimated): 0.11M kWh
1b

Resource mix

3.1M kWh owned + contracted
Base Resource: 1.31M kWh (42.1%)Generation - Slate (PV+BESS): 0.72M kWh (23.0%)Generation - Whitney Point: 0.70M kWh (22.5%)Generation - LEC: 0.39M kWh (12.4%)3.1MkWh total
ResourceEnergyShare
Base Resource1.31M42.1%
Generation - Slate (PV+BESS)0.72M23.0%
Generation - Whitney Point0.70M22.5%
Generation - LEC0.39M12.4%
1c

Cost composition

Gross total $0.55M

Gross costs before resource credits and allocated overheads, so this totals $0.55M rather than the $0.48M net figure in the KPI row above.

OverheadOverhead: $63,757$63,757DistributionDistribution: $151,556$151,556TransmissionTransmission: $58,609$58,609Grid MgmtGrid Mgmt: $13,509$13,509LoadLoad: $100,057$100,057Power ResourcesPower Resources: $163,903$163,903
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)2,924,555$100,057$03.42¢$100,057
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,313,346$42,982-$49,498-0.50¢-$6,516
Generation — LEC387,114$60,125-$20,78510.16¢$39,340
Generation — Astoria0$0$0—$0
Generation — Whitney Point701,084$40,959-$8,9994.56¢$31,960
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)716,676$41,340-$16,4493.47¢$24,892
Supplemental0-$644$0—-$644

Santa Clara Valley WDSCV

Metered load

20.6M kWh

vs 20.8M kWh budget

Total cost

$2.43M

vs $2.97M budget

Cost per kWh (w/o P3 or C&I)

11.83¢

vs 14.33¢ budget

Load covered by resource

74.1%

owned + contracted

1a

Monthly load, kWh

Santa Clara Valley WD

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.60M1.20M1.80M2.40M3.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 1.29M kWhFeb — 2025 actual: 1.19M kWhMar — 2025 actual: 1.33M kWhApr — 2025 actual: 1.48M kWhMay — 2025 actual: 1.84M kWhJun — 2025 actual: 2.03M kWhJul — 2025 actual: 2.12M kWhAug — 2025 actual: 2.26M kWhSep — 2025 actual: 2.19M kWhOct — 2025 actual: 2.04M kWhNov — 2025 actual: 1.33M kWhDec — 2025 actual: 1.13M kWhJan — 2026 budget: 1.35M kWhFeb — 2026 budget: 1.31M kWhMar — 2026 budget: 1.30M kWhApr — 2026 budget: 1.52M kWhMay — 2026 budget: 1.83M kWhJun — 2026 budget: 2.09M kWhJul — 2026 budget: 2.28M kWhAug — 2026 budget: 2.28M kWhSep — 2026 budget: 2.08M kWhOct — 2026 budget: 1.92M kWhNov — 2026 budget: 1.51M kWhDec — 2026 budget: 1.29M kWhJan — 2026 actual: 1.21M kWhFeb — 2026 actual: 1.19M kWhMar — 2026 actual: 1.55M kWhApr — 2026 actual: 1.61M kWhMay — 2026 actual: 1.89M kWhJun — 2026 actual: 1.99M kWhJul — 2026 actual: 2.12M kWhAug — 2026 actual: 2.11M kWhSep — 2026 actual: 1.98M kWhOct — 2026 actual (estimated): 2.11M kWhNov — 2026 actual (estimated): 1.50M kWhDec — 2026 actual (estimated): 1.29M kWh
1b

Resource mix

15.6M kWh owned + contracted
Base Resource: 7.69M kWh (49.4%)Generation - Slate (PV+BESS): 3.58M kWh (23.0%)Generation - Whitney Point: 2.10M kWh (13.5%)Generation - LEC: 1.11M kWh (7.1%)Generation - Astoria: 1.09M kWh (7.0%)15.6MkWh total
ResourceEnergyShare
Base Resource7.69M49.4%
Generation - Slate (PV+BESS)3.58M23.0%
Generation - Whitney Point2.10M13.5%
Generation - LEC1.11M7.1%
Generation - Astoria1.09M7.0%
1c

Cost composition

Gross total $2.84M

Gross costs before resource credits and allocated overheads, so this totals $2.84M rather than the $2.43M net figure in the KPI row above.

OverheadOverhead: $122,034$122,034DistributionDistribution: $781,698$781,698TransmissionTransmission: $306,841$306,841Grid MgmtGrid Mgmt: $65,303$65,303LoadLoad: $744,994$744,994Power ResourcesPower Resources: $816,065$816,065
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)21,009,829$744,994$03.55¢$744,994
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource7,688,914$270,176-$299,484-0.38¢-$29,308
Generation — LEC1,112,310$172,759-$59,72110.16¢$113,038
Generation — Astoria1,093,750$68,457-$14,9144.90¢$53,542
Generation — Whitney Point2,102,943$122,859-$26,9944.56¢$95,864
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)3,577,029$144,745-$64,5832.24¢$80,162
Supplemental0$98,025$0—$98,025

Sonoma County WASCWA

Metered load

34.6M kWh

vs 36.0M kWh budget

Total cost

$3.50M

vs $4.80M budget

Cost per kWh (w/o P3 or C&I)

10.10¢

vs 13.34¢ budget

Load covered by resource

74.1%

owned + contracted

1a

Monthly load, kWh

Sonoma County WA

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M1.00M2.00M3.00M4.00M5.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 2.14M kWhFeb — 2025 actual: 1.90M kWhMar — 2025 actual: 1.95M kWhApr — 2025 actual: 2.14M kWhMay — 2025 actual: 3.02M kWhJun — 2025 actual: 3.66M kWhJul — 2025 actual: 4.00M kWhAug — 2025 actual: 4.03M kWhSep — 2025 actual: 3.46M kWhOct — 2025 actual: 2.71M kWhNov — 2025 actual: 2.27M kWhDec — 2025 actual: 2.32M kWhJan — 2026 budget: 2.25M kWhFeb — 2026 budget: 2.13M kWhMar — 2026 budget: 2.37M kWhApr — 2026 budget: 2.51M kWhMay — 2026 budget: 3.20M kWhJun — 2026 budget: 3.73M kWhJul — 2026 budget: 4.02M kWhAug — 2026 budget: 3.91M kWhSep — 2026 budget: 3.57M kWhOct — 2026 budget: 3.26M kWhNov — 2026 budget: 2.67M kWhDec — 2026 budget: 2.36M kWhJan — 2026 actual: 2.11M kWhFeb — 2026 actual: 1.85M kWhMar — 2026 actual: 2.38M kWhApr — 2026 actual: 2.40M kWhMay — 2026 actual: 2.86M kWhJun — 2026 actual: 3.33M kWhJul — 2026 actual: 3.80M kWhAug — 2026 actual: 3.96M kWhSep — 2026 actual: 3.51M kWhOct — 2026 actual (estimated): 3.42M kWhNov — 2026 actual (estimated): 2.66M kWhDec — 2026 actual (estimated): 2.36M kWh
1b

Resource mix

26.0M kWh owned + contracted
Base Resource: 12.95M kWh (49.7%)Generation - Whitney Point: 7.85M kWh (30.2%)Generation - Astoria: 2.86M kWh (11.0%)Generation - Slate (PV+BESS): 2.38M kWh (9.1%)26.0MkWh total
ResourceEnergyShare
Base Resource12.95M49.7%
Generation - Whitney Point7.85M30.2%
Generation - Astoria2.86M11.0%
Generation - Slate (PV+BESS)2.38M9.1%
1c

Cost composition

Gross total $4.16M

Gross costs before resource credits and allocated overheads, so this totals $4.16M rather than the $3.50M net figure in the KPI row above.

OverheadOverhead: $169,513$169,513DistributionDistribution: $659,854$659,854TransmissionTransmission: $734,639$734,639Grid MgmtGrid Mgmt: $113,551$113,551LoadLoad: $1,251,666$1,251,666Power ResourcesPower Resources: $1,228,567$1,228,567
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)35,122,467$1,251,666$03.56¢$1,251,666
Specific Projects (BOR + WSH)0$9,159$0—$9,159
Base Resource12,946,179$453,345-$503,147-0.38¢-$49,802
Generation — LEC0$0$0—$0
Generation — Astoria2,857,840$178,870-$38,9704.90¢$139,900
Generation — Whitney Point7,851,337$458,692-$100,7824.56¢$357,910
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)2,381,588$68,954-$35,1991.42¢$33,755
Supplemental0$78,758$0—$78,758

West Stanislaus IDWSID

Metered load

16.6M kWh

vs 15.1M kWh budget

Total cost

$1.57M

vs $2.21M budget

Cost per kWh (w/o P3 or C&I)

9.49¢

vs 14.66¢ budget

Load covered by resource

87.6%

owned + contracted

1a

Monthly load, kWh

West Stanislaus ID

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.80M1.60M2.40M3.20M4.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.08M kWhFeb — 2025 actual: 0.21M kWhMar — 2025 actual: 0.67M kWhApr — 2025 actual: 1.67M kWhMay — 2025 actual: 2.18M kWhJun — 2025 actual: 1.90M kWhJul — 2025 actual: 2.08M kWhAug — 2025 actual: 2.26M kWhSep — 2025 actual: 1.31M kWhOct — 2025 actual: 0.67M kWhNov — 2025 actual: 0.20M kWhDec — 2025 actual: 0.06M kWhJan — 2026 budget: 0.13M kWhFeb — 2026 budget: 0.38M kWhMar — 2026 budget: 0.58M kWhApr — 2026 budget: 1.29M kWhMay — 2026 budget: 2.09M kWhJun — 2026 budget: 2.42M kWhJul — 2026 budget: 2.69M kWhAug — 2026 budget: 2.18M kWhSep — 2026 budget: 1.35M kWhOct — 2026 budget: 1.08M kWhNov — 2026 budget: 0.57M kWhDec — 2026 budget: 0.33M kWhJan — 2026 actual: 0.06M kWhFeb — 2026 actual: 0.27M kWhMar — 2026 actual: 1.46M kWhApr — 2026 actual: 2.43M kWhMay — 2026 actual: 3.09M kWhJun — 2026 actual: 2.40M kWhJul — 2026 actual: 2.51M kWhAug — 2026 actual: 2.15M kWhSep — 2026 actual: 1.29M kWhOct — 2026 actual (estimated): 0.00M kWhNov — 2026 actual (estimated): 0.57M kWhDec — 2026 actual (estimated): 0.33M kWh
1b

Resource mix

14.7M kWh owned + contracted
Base Resource: 9.05M kWh (61.6%)Generation - Slate (PV+BESS): 4.77M kWh (32.5%)Generation - LEC: 0.87M kWh (5.9%)14.7MkWh total
ResourceEnergyShare
Base Resource9.05M61.6%
Generation - Slate (PV+BESS)4.77M32.5%
Generation - LEC0.87M5.9%
1c

Cost composition

Gross total $1.97M

Gross costs before resource credits and allocated overheads, so this totals $1.97M rather than the $1.57M net figure in the KPI row above.

OverheadOverhead: $91,684$91,684DistributionDistribution: $578,991$578,991TransmissionTransmission: $173,913$173,913Grid MgmtGrid Mgmt: $65,793$65,793LoadLoad: $480,399$480,399Power ResourcesPower Resources: $575,013$575,013
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)16,763,536$480,399$02.87¢$480,399
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource9,046,381$276,068-$305,620-0.33¢-$29,553
Generation — LEC869,825$135,098-$46,70210.16¢$88,396
Generation — Astoria0$0$0—$0
Generation — Whitney Point0$0$0—$0
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)4,772,469$220,537-$93,9672.65¢$126,569
Supplemental0-$4,420$0—-$4,420

Westlands WDWWD

Metered load

88.5M kWh

vs 93.9M kWh budget

Total cost

$13.57M

vs $19.61M budget

Cost per kWh (w/o P3 or C&I)

15.32¢

vs 20.89¢ budget

Load covered by resource

130.1%

owned + contracted

1a

Monthly load, kWh

Westlands WD

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M4.00M8.00M12.00M16.00M20.00Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.85M kWhFeb — 2025 actual: 1.54M kWhMar — 2025 actual: 1.01M kWhApr — 2025 actual: 2.91M kWhMay — 2025 actual: 5.06M kWhJun — 2025 actual: 5.93M kWhJul — 2025 actual: 5.76M kWhAug — 2025 actual: 3.64M kWhSep — 2025 actual: 2.09M kWhOct — 2025 actual: 1.59M kWhNov — 2025 actual: 0.39M kWhDec — 2025 actual: 0.46M kWhJan — 2026 budget: 4.04M kWhFeb — 2026 budget: 7.98M kWhMar — 2026 budget: 5.85M kWhApr — 2026 budget: 9.88M kWhMay — 2026 budget: 15.95M kWhJun — 2026 budget: 15.09M kWhJul — 2026 budget: 12.11M kWhAug — 2026 budget: 9.08M kWhSep — 2026 budget: 4.87M kWhOct — 2026 budget: 4.42M kWhNov — 2026 budget: 2.33M kWhDec — 2026 budget: 2.28M kWhJan — 2026 actual: 0.66M kWhFeb — 2026 actual: 1.23M kWhMar — 2026 actual: 3.63M kWhApr — 2026 actual: 11.25M kWhMay — 2026 actual: 15.56M kWhJun — 2026 actual: 16.00M kWhJul — 2026 actual: 16.34M kWhAug — 2026 actual: 10.51M kWhSep — 2026 actual: 5.08M kWhOct — 2026 actual (estimated): 3.62M kWhNov — 2026 actual (estimated): 2.34M kWhDec — 2026 actual (estimated): 2.29M kWh
1b

Resource mix

123.0M kWh owned + contracted
Base Resource: 75.03M kWh (61.0%)District Specific Projects (BOR + WSH): 10.05M kWh (8.2%)Generation - Slate (PV+BESS): 9.56M kWh (7.8%)Generation - Astoria: 9.43M kWh (7.7%)Generation - Whitney Point: 8.41M kWh (6.8%)Generation - Luna Valley: 5.48M kWh (4.5%)Generation - LEC: 5.03M kWh (4.1%)123.0MkWh total
ResourceEnergyShare
Base Resource75.03M61.0%
District Specific Projects (BOR + WSH)10.05M8.2%
Generation - Slate (PV+BESS)9.56M7.8%
Generation - Astoria9.43M7.7%
Generation - Whitney Point8.41M6.8%
Generation - Luna Valley5.48M4.5%
Generation - LEC5.03M4.1%
1c

Cost composition

Gross total $16.72M

Gross costs before resource credits and allocated overheads, so this totals $16.72M rather than the $13.57M net figure in the KPI row above.

OverheadOverhead: $885,611$885,611DistributionDistribution: $6,332,066$6,332,066TransmissionTransmission: $1,933,196$1,933,196Grid MgmtGrid Mgmt: $378,899$378,899LoadLoad: $2,778,361$2,778,361Power ResourcesPower Resources: $4,416,147$4,416,147
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)94,557,595$2,778,361$02.94¢$2,778,361
Specific Projects (BOR + WSH)10,052,000$17,015-$160,930-1.43¢-$143,915
Base Resource75,030,158$2,239,392-$2,576,495-0.45¢-$337,103
Generation — LEC5,031,545$781,469-$270,14810.16¢$511,322
Generation — Astoria9,432,962$590,401-$128,6284.90¢$461,773
Generation — Whitney Point8,412,081$491,452-$107,9804.56¢$383,472
Generation — Luna Valley5,477,582$113,377-$27,6991.56¢$85,678
Generation — Slate (PV+BESS)9,556,686$540,244-$216,2343.39¢$324,011
Supplemental0-$27,962$0—-$27,962

Zone 7 WAZ7

Metered load

4.1M kWh

vs 6.2M kWh budget

Total cost

$0.60M

vs $1.02M budget

Cost per kWh (w/o P3 or C&I)

14.77¢

vs 16.42¢ budget

Load covered by resource

86.9%

owned + contracted

1a

Monthly load, kWh

Zone 7 WA

Sep is the last actual month. October–December is carried at budget, so the two 2026 lines coincide across those months.

2026 actual2026 budget2025 actualestimated months
0.00M0.14M0.28M0.42M0.56M0.70Mestimated →JanFebMarAprMayJunJulAugSepOctNovDecJan — 2025 actual: 0.32M kWhFeb — 2025 actual: 0.29M kWhMar — 2025 actual: 0.34M kWhApr — 2025 actual: 0.47M kWhMay — 2025 actual: 0.44M kWhJun — 2025 actual: 0.41M kWhJul — 2025 actual: 0.45M kWhAug — 2025 actual: 0.45M kWhSep — 2025 actual: 0.55M kWhOct — 2025 actual: 0.30M kWhNov — 2025 actual: 0.25M kWhDec — 2025 actual: 0.27M kWhJan — 2026 budget: 0.49M kWhFeb — 2026 budget: 0.54M kWhMar — 2026 budget: 0.43M kWhApr — 2026 budget: 0.45M kWhMay — 2026 budget: 0.53M kWhJun — 2026 budget: 0.47M kWhJul — 2026 budget: 0.53M kWhAug — 2026 budget: 0.58M kWhSep — 2026 budget: 0.61M kWhOct — 2026 budget: 0.61M kWhNov — 2026 budget: 0.58M kWhDec — 2026 budget: 0.38M kWhJan — 2026 actual: 0.22M kWhFeb — 2026 actual: 0.21M kWhMar — 2026 actual: 0.36M kWhApr — 2026 actual: 0.34M kWhMay — 2026 actual: 0.31M kWhJun — 2026 actual: 0.35M kWhJul — 2026 actual: 0.39M kWhAug — 2026 actual: 0.35M kWhSep — 2026 actual: 0.29M kWhOct — 2026 actual (estimated): 0.27M kWhNov — 2026 actual (estimated): 0.59M kWhDec — 2026 actual (estimated): 0.39M kWh
1b

Resource mix

3.6M kWh owned + contracted
Base Resource: 1.45M kWh (40.1%)Generation - Slate (PV+BESS): 1.19M kWh (33.0%)Generation - Whitney Point: 0.56M kWh (15.5%)Generation - Astoria: 0.41M kWh (11.4%)3.6MkWh total
ResourceEnergyShare
Base Resource1.45M40.1%
Generation - Slate (PV+BESS)1.19M33.0%
Generation - Whitney Point0.56M15.5%
Generation - Astoria0.41M11.4%
1c

Cost composition

Gross total $0.69M

Gross costs before resource credits and allocated overheads, so this totals $0.69M rather than the $0.60M net figure in the KPI row above.

OverheadOverhead: $75,289$75,289DistributionDistribution: $236,728$236,728TransmissionTransmission: $57,029$57,029Grid MgmtGrid Mgmt: $12,650$12,650LoadLoad: $150,501$150,501Power ResourcesPower Resources: $154,742$154,742
Resource portfolio detail · 9 resource lines, energy, cost, credit and ¢/kWh
ResourceEnergy (kWh)CostsCredits¢ / kWhNet
CAISO Load (DLF-adjusted)4,149,782$150,501$03.63¢$150,501
Specific Projects (BOR + WSH)0$0$0—$0
Base Resource1,446,434$51,623-$57,737-0.42¢-$6,114
Generation — LEC0$0$0—$0
Generation — Astoria409,787$25,648-$5,5884.90¢$20,060
Generation — Whitney Point560,744$32,760-$7,1984.56¢$25,562
Generation — Luna Valley0$0$0—$0
Generation — Slate (PV+BESS)1,190,546$34,470-$17,5931.42¢$16,877
Supplemental0$11,814$0—$11,814
Authority-wide
2

Funds available as of September 30, 2026

Total $13.79M

Participant-attributable balances only; excludes Board-approved reserves, working capital and CAISO collateral. Bars are scaled to each participant’s own total, so segment widths compare the mix of funds, not the amount — amounts are the dollar figures shown.

P3 available Cap & Invest available Funds on deposit
0%25%50%75%100%Arvin-Edison WSDArvin-Edison WSD — P3 available: $268,264 (42.2%)$268,264Arvin-Edison WSD — Cap & Invest available: $366,700 (57.8%)$366,700$0.63MBanta-Carbona IDBanta-Carbona ID — P3 available: $13,231 (100.0%)$13,231$0.01MByron-Bethany IDByron-Bethany ID — P3 available: $29,112 (33.5%)$29,112Byron-Bethany ID — Funds on deposit: $57,887 (66.5%)$57,887$0.09MCawelo WDCawelo WD — P3 available: $222,954 (22.8%)$222,954Cawelo WD — Cap & Invest available: $252,593 (25.8%)$252,593Cawelo WD — Funds on deposit: $503,490 (51.4%)$503,490$0.98MGlenn-Colusa IDGlenn-Colusa ID — P3 available: $99,984 (45.8%)$99,984Glenn-Colusa ID — Funds on deposit: $118,183 (54.2%)$118,183$0.22MJames IDJames ID — P3 available: $34,945 (11.3%)$34,945James ID — Cap & Invest available: $197,393 (63.7%)$197,393James ID — Funds on deposit: $77,619 (25.0%)$77,619$0.31MLower Tule River IDLower Tule River ID — P3 available: $111,141 (24.5%)$111,141Lower Tule River ID — Cap & Invest available: $159,892 (35.3%)$159,892Lower Tule River ID — Funds on deposit: $181,788 (40.1%)$181,788$0.45MPrinceton Prov IDPrinceton Prov ID — P3 available: $10,203 (8.8%)$10,203Princeton Prov ID — Cap & Invest available: $105,546 (91.2%)$105,546$0.12MRD108RD108 — P3 available: $34,739 (25.8%)$34,739RD108 — Funds on deposit: $100,000 (74.2%)$100,000$0.13MSanta Clara Valley WDSanta Clara Valley WD — P3 available: $24,711 (4.3%)$24,711Santa Clara Valley WD — Cap & Invest available: $34,272 (6.0%)$34,272Santa Clara Valley WD — Funds on deposit: $513,428 (89.7%)$513,428$0.57MSonoma County WASonoma County WA — P3 available: $389,346 (18.7%)$389,346Sonoma County WA — Cap & Invest available: $983,193 (47.3%)$983,193Sonoma County WA — Funds on deposit: $704,570 (33.9%)$704,570$2.08MWest Stanislaus IDWest Stanislaus ID — P3 available: $103,578 (9.2%)$103,578West Stanislaus ID — Cap & Invest available: $742,097 (65.8%)$742,097West Stanislaus ID — Funds on deposit: $282,746 (25.1%)$282,746$1.13MWestlands WDWestlands WD — P3 available: $900,719 (13.6%)$900,719Westlands WD — Cap & Invest available: $5,593,270 (84.5%)$5,593,270Westlands WD — Funds on deposit: $127,894 (1.9%)$127,894$6.62MZone 7 WAZone 7 WA — P3 available: $56,009 (12.7%)$56,009Zone 7 WA — Cap & Invest available: $239,988 (54.3%)$239,988Zone 7 WA — Funds on deposit: $145,637 (33.0%)$145,637$0.44MShare of each participant’s available funds · dollar total at right

Total funds available

$13.79M

P3 available

$2.30M

Cap & Invest available

$8.67M

Funds on deposit

$2.81M

Funds available detail · all 14 participants
Participant P3Cap & InvestOn deposit Total available
Arvin-Edison WSD$268,264$366,700$0$634,964
Banta-Carbona ID$13,231$0$0$13,231
Byron-Bethany ID$29,112$0$57,887$87,000
Cawelo WD$222,954$252,593$503,490$979,037
Glenn-Colusa ID$99,984$0$118,183$218,167
James ID$34,945$197,393$77,619$309,957
Lower Tule River ID$111,141$159,892$181,788$452,821
Princeton Prov ID$10,203$105,546$0$115,749
RD108$34,739$0$100,000$134,739
Santa Clara Valley WD$24,711$34,272$513,428$572,410
Sonoma County WA$389,346$983,193$704,570$2,077,110
West Stanislaus ID$103,578$742,097$282,746$1,128,421
Westlands WD$900,719$5,593,270$127,894$6,621,883
Zone 7 WA$56,009$239,988$145,637$441,634
3

Business unit activities — October 2026

Financial

Board packet financials; vendor payments; processed and mailed Reconciliation checks; coordination with GM on ARB allowance consignments; participate at October Board meeting.

Administrative

Staff coordination; supporting AI implementation across all business units; participate at October Board meeting; Board meeting packet preparation for October Board Meeting; 2027 Budget support; Project development support; Participation on WAPA committees.

Compliance

RA policy development. SQMD verification. Annual RA filing for 2027.

Operations

Daily operations; developing 2027 budget; participate at October Board meeting; POI additions/terminations; displacement program.

Project Development

Incorporating engineering services in collaborative participation with Project Participants on 7 distributed solar facilities, 2 substations and 3 distribution intervening facilities; POI addition/removal support; aux load meetings on mobile batteries.

Legal

PPA and license modifications for distributed solar regarding interconnection status; building conformed copies of all PG&E service agreements and associated WAPA versions; participate at October Board Meeting.